Gold'n Plump Cold Spring - Executive Summary

| Accident History | Chemicals | Emergency Response | Registration | Source | Executive Summary |

1.0    SOURCE AND PROCESS DESCRIPTION 
The Gold'n Plump Poultry Cold Spring facility (Cold Spring facility) in Cold Spring, Minnesota is subject to the USEPA's Risk Management Program (RMP) for Accidental Chemical Release regulations (40 CFR 68) because it has a refrigeration system that contains more than the threshold quantity (10,000 pounds) of anhydrous ammonia (CAS Number 7664-41-7).  The anhydrous ammonia (ammonia) refrigeration system is used to control the temperature for chicken processing and packaging.  The entire system contains approximately 20,000 pounds of ammonia in various physical states (gas, liquid, and saturated vapor).  The largest vessel is the high pressure receiver that operates at 200 psig and can contain as much as 9,000 pounds of liquid ammonia, assuming a 90 percent fill volume.  However, during typical operation, the vessel holds only 4,500 pounds. 
2.0    POTENTIAL RELEASE SCENARIOS 
As required by the RMP rule requirements, two specifically defined release scenar 
ios (a worst-case release and an alternative-case release) were analyzed to determine the maximum distance to an endpoint where the ammonia concentration is 200 parts per million in air, or 0.02 percent.  The release scenarios analyzed are based upon the guidance contained in the USEPA's Model Risk Management Program and Plan for Ammonia Refrigeration (the "Model Plan"), dated May 1996.   
 
2.1    Worst-case Release 
The worst-case release is considered to be defined by the catastrophic rupture and complete loss of the contents of the largest vessel and associated piping (approximately 9,000 pounds of ammonia) over a 10-minute period.  Using the specified worst-case meteorology contained in the "Model Plan" and assuming the facility is located in a rural area, the distance to the endpoint for a worst-case release extends beyond the facility boundary.   
 
Although the worst-case consequence analysis is required by the RMP, it should be considered a highly unlikely event.  Design, construction 
, and operation of the high pressure receiver is such that catastrophic failure is extremely remote.  The receiver was designed and constructed in strict accordance with the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code (Section VIII), and was certified and stamped by the National Board of Pressure Vessel Inspectors (National Board).  Third party and state mandated inspections of the vessel's condition occurs every year by a Travelers Insurance Company inspector. 
 
The vessel is operated well below the design pressure (i.e., maximum allowable working pressure) and because of the safety factors built into the ASME Code, a fourfold pressure excursion would have to occur before catastrophic vessel failure.  If this were to occur, the vessel is equipped with dual safety relief valves (SRVs) set to relieve internal pressure at 150 psig.  A high pressure excursion would not occur as long as the SRVs continued to function.  Actuation of the SRVs would result i 
n an ammonia release similar to that described in Section 2.2 for the alternative release scenario.  The SRVs are replaced every five years, in accordance with the International Institute of Ammonia Refrigeration (IIAR) guidance contained in IIAR Bulletin Number 109, Minimum Safety Criteria for a Safety Ammonia Refrigeration System, to ensure that they will function properly when required. 
 
The worst-case release scenario is unlikely for the following additional reasons: 
 
7 The facility has a preventive maintenance program in place to maintain the ongoing integrity of the vessels; 
7 The facility has a training program designed to ensure that the system is operated by qualified personnel; 
7 Main ammonia shut-offs have been labeled to allow personnel to stop the flow of ammonia quickly in an emergency. 
 
2.2    Alternative-case Release 
The alternative-case release scenario is considered to be defined by a release of ammonia that is more likely to occur than the worst-case scenario, and reach 
es an endpoint offsite.   
 
The "Model Plan" scenario was used for this analysis, which assumes a release of ammonia through a <-inch effective diameter hole in a high side (i.e., 150 psig) pipe or vessel, releasing 100 pounds of ammonia per minute.  Using the specified meteorology contained in the "Model Plan", the distance to the endpoint for the "more likely" release scenario extends beyond the facility boundary. 
 
The alternative release scenario is unlikely for the following reasons: 
 
7 Industrial standards were followed for the manufacture and quality control of these lines; 
7 The facility has a preventive maintenance program in place to maintain the ongoing integrity of the system; and 
7 The facility has a training program designed to ensure that the system is operated by qualified personnel. 
3.0    PREVENTION PROGRAM 
The facility has carefully considered the potential for accidental releases of ammonia, such as the occurrence of the worst-case and alternative-case release scenarios  
described in Section 2.0.  To help minimize the probability and severity of an ammonia release, a prevention program that satisfies the Occupational Safety and Health Administration (OSHA), Process Safety Management (PSM) of Highly Hazardous Chemicals (29 CFR 1910.119) has been implemented.  The key components of the prevention program are summarized below: 
 
7 The development of an employee participation program, which includes Cold Spring facility employees from all areas within the plant. 
7 The development, documentation, and operator availability of critical process safety information regarding the hazards of ammonia, the design basis of the system, and the equipment.  This information is used to fully understand and safely operate the ammonia refrigeration system. 
7 The performance of a formal process hazard analysis (PHA) on the ammonia refrigeration system using a "What-If" Protection Analysis.  A team with expertise in engineering, operations, maintenance, and safety evaluated t 
he existing refrigeration system in depth and developed recommendations to improve the safety and operability of the system.  The PHA is updated and revalidated every five years. 
7 Standard operating procedures (SOPs) are used to provide the basis for proper and safe operation of the ammonia refrigeration system.  The SOPs include procedures for normal operations, startup, shutdown, emergency operations, and emergency shutdown.  They also describe safe operating limits for temperature and pressure, the consequences of operating outside these safe operating limits, and a description of safety systems and how they operate. 
7 Refrigeration system operators receive refresher training at least every three years.  The training content is based on the process safety information and operating procedures.  The training program ensures that the operators understand the nature and causes of problems arising from system operations and serves to increase awareness with respect to the hazards partic 
ular to ammonia and the refrigeration process. 
7 Contractors that are hired to work on, or adjacent to, the refrigeration system are "pre-qualified" based on their knowledge of ammonia refrigeration, understanding of applicable codes and standards, and their demonstrated ability to work safely.  In addition, these contractors are periodically evaluated to ensure that they continue to work safely. 
7 A preventative maintenance program is in place at the Cold Spring facility.  This includes regular inspection of major powered equipment, including compressors, pumps and large fans, bearings, couplings, shaft seals, mountings, etc., for vibration or incipient mechanical failure, and regular inspection and calibration of liquid level sensors, temperature and pressure instruments, switches and shutdown devices that have safety implications. 
7 Formal authorization systems (i.e., management of change procedure, pre-startup safety review) are in place to ensure that system changes or expansions  
are as safe as the original design and that an independent recheck confirms that the changes are consistent with the engineering design and in a condition to be safely operated prior to startup. 
7 Events that might cause an accidental or unexpected release of ammonia are subjected to a formal investigation.  The objective of the investigation is to correct deficiencies in such a way as to prevent recurrence. 
7 Prior to the performance of any hot work (i.e., spark or flame producing operations such as welding, cutting, brazing, grinding), management must approve the work by executing a written hot work authorization permit to verify that precautions to prevent fire have been implemented. 
7 Planning with the local fire department to ensure a rapid response to potential incidents with the system or external events, such as floods or tornadoes. 
7 Adherence to fire codes and preparation for fires, storms, or events which could impact the ammonia system. 
7 Prevention program compliance audit 
s performed every three years to verify that the appropriate management systems are in place and are being properly implemented.  Any deficiency found in an audit is corrected. 
4.0    ACCIDENT HISTORY 
There have been no accidental releases of ammonia at the facility in the last five years that have resulted in death, injury, or significant property damage on site or off-site death, injury, evacuation, sheltering in place, property damage, or environmental damage. 
 
5.0    EMERGENCY RESPONSE PROGRAM 
The Cold Spring facility has implemented a detailed written Emergency Response Plan (ERP).  The ERP is intended to address all emergencies at the facility, in addition to incidents related to a release of ammonia.
Click to return to beginning