1.0 EXECUTIVE SUMMARY 
 
1.10 Accidental Release Prevention And Emergency Response Policies 
 
The Underwood Fruit & Warehouse Company refrigeration system uses pure anhydrous ammonia (a commonly used refrigerant for industrial systems) as the refrigerant.  Given the quantity handled, anhydrous ammonia is considered a hazardous substance by EPA.  Many of the properties that make ammonia valuable as a refrigerant also requires that precautions and procedures be in place to protect employee and public health and safety during a chemical emergency.  It is the policy of Underwood Fruit & Warehouse to be in compliance with all applicable federal and state rules and regulations.     
 
Safety at our facility is inherent on the manner in which anhydrous ammonia is handled.  While the design of the facility incorporates a multitude of safety devices, safe handling procedures combined with appropriate training of our personnel are key aspects to maintaining safety at our facility. 
 
We will have a wr 
itten Process Safety Management (PSM) plan that complies with the regulations stipulated by WAC 296-67-017.  A crucial component of this plan is the Emergency Response Plan, developed in compliance with the Emergency Response provisions of WAC 296-62-3112.  The Emergency Response Plan includes pre-emergency planning and coordinating with outside parties.  This enables those who deal with emergencies to have a course of action to effectively deal with unplanned events.  Anticipated completion date of these plans is October, 1999. 
 
1.20 Facility Description And Substances Handled 
 
7 Underwood Fruit & Warehouse stores and distributes fruits.  Storage and distribution requires the use of a refrigeration system to preserve the integrity of the fruits.  This refrigeration process uses ammonia as a refrigerant.  Access to the facility is restricted to authorized employees, management personnel, and contractors. 
7 The regulated substance handled at this facility is anhydrous ammonia. 
7 The amm 
onia refrigeration system maximum inventory is 13,893 pounds of anhydrous ammonia.  There is no standby make-up inventory kept on-site. 
 
1.30 The worst-case release scenario(s) and the alternative release scenario(s), including administrative controls and mitigation measures to limit the distances for each reported scenario.  
 
Release scenarios were modeled using RMP*Comp (Version 1.06), a software program developed by the National Oceanic and Atmospheric Administration (NOAA) and EPA.  Offsite receptors were defined using the LandView III (Version 1.0) system.  This system estimates residential population within the circle defined by the endpoint of the worst-case and alternative release scenarios.  In addition, it lists whether certain types of public receptors and environmental receptors are within the circles. 
 
7 Worst-Case Scenario.  Catastrophic failure of the medium pressure receiver located in the Main Engine Room when filled to the greatest amount would release 9,200 pounds of 
liquid ammonia.  This scenario presumes that the entire contents are released.   
 
The distance to the toxic endpoint for the worst-case scenario is 1.3 miles from the point of release.  This distance extends beyond the facility fence line, and would encompass a population of 2,700 with the closest residence approximately <  mile from the site.  A school and hospital are about = mile away, inside of this release zone.  The Columbia River, a city park, a restaurant, and a store are within close proximity of the facility.  No other public or environmental receptors are located within this zone.  
 
This worst-case scenario would not likely occur unless an act of nature (e.g., earthquake) physically compromised the tank.   The structural integrity of the tank is safeguarded by periodic inspection for mechanical integrity to prevent a rupture due to tank degradation.  The tank is also safeguarded from rupture from over-pressurization.  It is a rated pressure vessel hydro-tested to 375 psi a 
nd equipped with 250 psi pressure relief valves. The design specification of the tank only allows a maximum capacity of 80% at 800F, limiting the total amount of ammonia in the system.  During high demand, the High Pressure Receiver may only be filled to a fraction (~30%) of capacity.  In addition, predominant winds are significantly stronger than input into the modeling program, helping to dispense the vapors more rapidly. 
 
7 Alternative Scenario. Several alternative scenarios can generate the equivalent of a 1" opening in a high pressure liquid line.  Alternative scenarios could include an opening created by a valve sheared off, a large gasket leak, or a pressure relief valve release.  These scenarios presumes a release duration of 10 minutes resulting in a loss of 14,000 pounds of liquid ammonia.  This scenario was selected because a release of this type would occur outdoors resulting in the highest potential exposure to offsite receptors. 
 
The distance to the toxic endpoint for the 
alternative scenario is 0.7 mile from the point of release.  This distance extends beyond the facility fence line, and would encompass a population of 500 with the closest residence approximately <  mile from the site.  A school and hospital are about = mile away, inside of this release zone. The Columbia River, a city park, a restaurant, and a store are within close proximity of the facility.  No other public or environmental receptors are located within this zone.  
 
The severity of release from this scenario would likely be less since safety system provisions are in place to limit the release duration to less than ten minutes through the use of appropriately placed isolation valves.  In addition, predominant winds are significantly stronger than input into the modeling program, helping to dispense the vapors more rapidly. 
 
1.40 General Accidental Release Prevention Program And Chemical-Specific Prevention Steps  
 
Underwood Fruit & Warehouse complies with EPA's Accidental Release Pre 
vention Rule and with all applicable state codes and regulations.  The design and construction of this facility was in accordance with published standards, tests or recommended methods of trade, industry or governmental organizations.   
 
Underwood Fruit & Warehouse's written PSM plan will incorporate many policies and procedures to ensure safe operation and maintenance of this facility.  Plan elements essential to safe operation of the refrigeration system include employee participation, process hazard information, process hazard analysis, operating procedures, training, contractor safety, pre-startup safety review, mechanical integrity, management of change, hot-work permits, incident investigation, emergency response and planning, and compliance audits.  This plan will be reviewed annually and updated as necessary by the Underwood Fruit & Warehouse Safety Supervisor.  
 
Training is provided to ensure that each employee involved in operating a process has been trained in an overview of 
the process, the operating procedures, and safety considerations.  This training uses guidelines developed by the International Institute of Ammonia Refrigeration (IIAR) and Refrigeration Engineers Technology Association (RETA).  Only qualified maintenance personnel operate and interact with the refrigeration system.  This minimizes the chances of inadvertent error in operation that could lead to a release of ammonia.  Startup, shutdown, and any onstream adjustments are handled by these qualified persons.   
 
1.50 Five-Year Accident History 
 
There has been no significant release of ammonia at Underwood Fruit & Warehouse in the past five years. 
 
1.60 Emergency Response Program 
 
Underwood Fruit & Warehouse will have a written Emergency Response Plan developed to ensure that precautions and procedures are in place to protect employee and public health and safety during a chemical emergency.  It complies with the provisions of WISHA Emergency Response regulations, WAC 296-62-3112.  The Em 
ergency Response Plan includes pre-emergency planning and coordinating with outside parties. This enables those who deal with emergencies to have a course of action to effectively deal with unplanned events.  This plan will be reviewed with the Bingen Fire Department. 
 
The approach in the development of this plan has been to identify the ammonia emergencies most likely to occur at Underwood Fruit & Warehouse and establish precautions and procedures to protect life safety and health during an emergency.  The refrigeration process has back-up prevention systems to keep processing malfunctions from becoming ammonia release emergencies.  If an emergency does occur, the following response personnel, facilities, and equipment are in place: 
 
7 Incident Command Center 
7 Emergency Alarm and Communication System 
7 Emergency Response Team 
7 Safe Rooms, Evacuation Plans, and Assembly Points 
7 Personal Protective Equipment 
 
The role and procedures for obtaining external emergency assistance have be 
en formally established with the Bingen Fire Department, including the LEPC Department of Emergency Services stationed in Klickitat County.  The Emergency Response Plan also includes procedures for notification of any potentially affected neighbors.   
 
All Underwood Fruit & Warehouse personnel will be trained to fulfill their designated responsibilities in an emergency.  Mock emergency drills will be held periodically to maintain familiarity with response actions and identify plan elements requiring improvement. 
 
This plan will be reviewed annually and updated as necessary by the Underwood Fruit & Warehouse Safety Supervisor. 
 
1.70 Planned Changes To Improve Safety 
 
This facility started production operations in 1952.  All system components meet design specifications in ANSI/IIAR, equipment, design, and installation of ammonia mechanical refrigerating systems.  All pressure vessels are built according to American Society of Mechanical Engineers (ASME), ASME Boiler and Pressure Vessel C 
ode, pressure vessels.  Any upgrades or extensive maintenance work performed in the future will be in compliance with those standards applicable at that time. 
 
All Underwood Fruit & Warehouse personnel are trained to fulfill their designated responsibilities in an emergency.  Mock emergency drills will be held periodically to maintain familiarity with response actions and identify elements requiring improvement. 
 
Process Hazard Analysis (PHA) Recommendations Resolution identified training forklift drivers on ammonia piping and hazards and investigate guarding/marking evaporators.  This is due in November, 1999.
Click to return to beginning