Authority of the Borough of Charleroi - Executive Summary

| Accident History | Chemicals | Emergency Response | Registration | Source | Executive Summary |

EXECUTIVE SUMMARY 
 
 
1. Purpose 
 
Chlorine is used as a disinfectant in water treatment.  Raw water contains microorganisms that are harmful to human health.  Several treatment processes are utilized at the plant to treat the raw water and a chlorination system provides disinfection of the water prior to discharge into the distribution system. 
 
2. Storage 
 
Chlorine is delivered to the treatment plant in one-ton containers.  A maximum of 4 one-ton containers of liquid chlorine are stored on site in the chlorine storage room. 
 
3.  Overview of the Water Treatment Plant 
 
The Authority of the Borough of Charleroi (ABC) Water Treatment Plant treats approximately 6 million gallons per day (MGD) of raw water at the treatment plant.  The chlorine used for disinfection is supplied from one-ton containers.  A maximum of four one-ton containers of liquid chlorine are stored on site.  This is the only chemical substance at this facility that is regulated under U. S. EPA's Accidental Release Preventi 
on Program. 
 
Chlorine gas is primarily a respiratory irritant.  In sufficient concentrations, the gas irritates the mucous membranes, the respiratory tract and the eyes.  In extreme cases difficulty in breathing may increase to the point where death can occur from respiratory collapse or lung failure.  The characteristic, penetrating odor of chlorine gas usually gives warning of its presence in the air.  At high concentrations, it is visible as a greenish yellow gas.  Liquid chlorine in contact with the skin or eyes will cause chemical burns and/or frostbite. 
 
Chlorine containers are thoroughly inspected for mechanical integrity and leaking valves prior to leaving the supplier's premises.  The containers are off-loaded from the delivery truck at the treatment plant by an overhead crane with a lifting beam that is specially designed for ton-containers.  The off-loaded containers are also inspected by ABC personnel. There are two identical systems that can deliver chlorine gas, at the  
correct flow rate, to the water.  Both systems operate simultaneously with one designated for pre-chlorination and one designated for post-chlorination.    
 
The liquid chlorine leaves the ton container as a gas.  There are two containers connected to a common pipe (manifold), however, only the chlorine gas valve on one container is normally open.  This container is used until empty and then the other container is put in service.  There are two chlorinators that are connected to the manifold and they regulate the flow of chlorine gas to the water.  Both chlorinators are used simulataneously in order to supply chlorine for pre-chlorination and post-chlorination.  The chlorine gas flows from the container to the manifold and then to the chlorinators.  The chlorine gas is drawn from the chlorinators by inducing a vacuum in the lines after the chlorinators.  The flow of water through an eductor creates a vacuum in the lines and also mixes the chlorine gas with the water.  If the water suppl 
y to the eductor is stopped, or the operating vacuum is lost for any other reason, the vacuum regulators in the chlorinators immediately close to isolate the chlorinators from the chlorine gas supply.  The average chlorine usage is 100 pounds per day. 
 
4.  Accidental Release Prevention 
 
Accidental releases of chlorine are prevented by routine training and adhering to the written operating procedures that cover the chlorination system from the ton-container unloading through the mixing of the chlorine gas with the water.  These procedures cover normal operations and emergency operations where personnel may have to respond to an accidental release of chlorine.  The chlorine system is inspected at least once per shift and leak testing is performed on the valves and fittings when ton-containers are changed-out and at other times if a leak is suspected.  Employees that are responsible for disconnecting empty containers and connecting filled containers to the chlorination system have been tr 
ained on the operating procedures, inspection of valves, fittings, and the connected piping, and leak testing with an aqueous ammonia solution.  Aqueous ammonia reacts with chlorine gas to form a very visible white cloud. An outside contractor inspects the chlorination system and performs preventive maintenance on this system as needed.  This insures that worn or damaged parts are replaced and routine maintenance is performed on the chlorinators and other equipment.  These preventive measures have resulted in the absence of any accidental release of chlorine that resulted in personal injury or property damage in the last five years. 
 
The water treatment plant maintains two sets of Self-Contained Breathing Apparatus (SCBA) and one set of The Chlorine Institute's Emergency Kit "B" for ton containers.  This equipment is stored in a room that is adjacent to the room that houses the ton containers.  ABC personnel receive annual training on the use of the breathing apparatus and the emergenc 
y kit.  In addition, ABC personnel plan to implement procedures that require employees to wear the SCBA equipment while disconnecting and changing the ton-containers.  Kit "B" contains the necessary tools and other equipment to contain valve leaks and repair small holes in a ton container, and capping devices for the fusible plugs in each end of the container.  Ton containers are equipped with six fusible metal plugs, three in each end.  The fusible metal is designed to melt between 158 and 165 degrees F to relieve pressure and prevent rupture of the container in case of fire or other exposure to high temperature.   
 
Chlorine gas is heavier than air and will settle to the lowest elevation when released.  The chlorine storage area is equipped with an exhaust fan that is mounted on an outside wall.  There are also air intake vents located near the floor so that the chlorine gas will be vented outside the building.  A switch to activate the fan is located outside, next to the door to the  
chlorine storage room.  Two exit doors are provided in the chlorine storage room.   
 
5.  Emergency Response Plan 
 
The ABC has developed an Off-Site Response Plan in the event of an accidental release of chlorine at the water treatment plant.  This Off-Site Response Plan has been submitted to the Local Emergency Planning Committee of Washington County and the Pennsylvania Emergency Response Commission for review and approval.  Once approved, the ABC Off-Site Response Plan will be included in the written community emergency response plan.  This plan was developed in accordance with the provisions set forth in Title III of the Superfund Amendments and Reauthorization Act of 1986.  The plan assigns release response procedures to the emergency coordinator at the ABC, Washington County Emergency Control, Charleroi Volunteer Fire Department, Local Police, Emergency Medical Services, and the Washington County Emergency Management Coordinator.  The plan is updated as necessary, including the li 
st of emergency telephone numbers.  The Charleroi Volunteer Fire Department has visited the treatment plant on several occasions and has trained ABC personnel on the proper use of the SCBA equipment. 
 
If a chlorine leak develops in a ton-container or in the connected piping, valves, or other equipment, a chlorine monitor in the chlorine storage area will activate an audible alarm in this area and in the adjacent Pump Station building which is manned 24-hours a day.  The treatment plant emergency operating procedures will be followed to determine the severity of the chlorine release and whether or not the gas may migrate offsite.  If the chlorine release may travel offsite, then the Offsite-Response Plan will be activated.  If the chlorine release does not pose a threat to the general public, ABC personnel will repair the leak.  ABC personnel have installed a windsock near the chlorine storage building so that the area that is likely to be affected by a chlorine release can be determine 
d.       
 
 
6.  Worst-Case and Alternate-Case Accidental Release Scenarios 
 
Worst-Case Release Scenario 
The worst-case release scenario as postulated in the regulation (40 CFR 68.25) is the release of the greatest quantity (of chlorine) in a single vessel.  The entire contents of this vessel are assumed to be released as a gas over a 10-minute period.  The largest single vessel at the treatment plant is a one-ton container; therefore, 2,000 pounds of liquid chlorine will be released as a gas over a 10-minute period.  A release of this magnitude would only be possible if the shell of the container failed and the liquid chlorine formed a pool and vaporized over a 10-minute period.  The likelihood of this type of catastrophic release is very minimal.  The off site consequence of this release was determined by use of U. S. EPA's RMP*Comp software.  The RMP*Comp results indicate that the chlorine concentration will exceed 3 parts per million (ppm) out to a radial distance of 1.3 miles from t 
he chlorine storage room. This is the distance to the toxic endpoint. Beyond 1.3 miles the chlorine concentration will be less than 3 ppm. Short-term exposure to chlorine concentrations less than 3 ppm is not considered to be a health hazard. Based on the guidance provided in the regulation and U. S. EPA's Risk Management Program Guidance for Wastewater Treatment Plants, the area surrounding the treatment plant was classified as urban due to the presence of nearby buildings and other structures, trees, and hilly terrain.  The meteorological conditions associated with the worst-case release scenario, as prescribed in the regulation, is a wind speed of 1.5 meters per second (3.36 miles per hour) and very stable atmospheric conditions. These stable atmospheric conditions will limit the mixing of the chlorine gas with the ambient air as the gas travels downwind from the point of release.  The cloud formed by the chlorine release will grow in size and decrease in concentration as it travels 
downwind.  
 
Alternate-Release Scenario 
The alternate release scenario is one that is more likely to occur than the worst case release scenario.  For this scenario, it was assumed that a 3/8-inch, type K copper transfer hose that connects the ton container to the manifold is sheared off and mitigation occurs in one hour.   This assumption is based on the alternate release scenarios listed in Edition 3 of The Chlorine Institute Pamphlet No. 74 - Estimating the Area Affected by a Chlorine Release, April 1998.  More than half of the contents of the ton-container (1,260 pounds) is released over a one-hour period.  For this scenario, the meteorological conditions prescribed in the regulation are neutral atmospheric stability conditions and a wind speed of 3 meters per second (6.7 miles per hour).   RMP*Comp was also used to determine the radial distance at which the chlorine concentration falls off to less than 3 ppm.  This distance to the toxic endpoint, as determined by RMP*Comp, is 0.10  
miles (528 feet).  It is unlikely that the entire contents of a ton-container would be released prior to ABC personnel closing the shutoff valve on the ton container.  Actual response time to shut off the valve is estimated to be 15 minutes.  
 
The worst-case and alternate release scenarios are summarized in Table 1 along with some additional information regarding population estimates, schools, hospitals and other building or recreation areas within the radial distance to the toxic endpoint.  Census data and the location of schools, hospitals, etc. were obtained from the LandView III mapping system that includes database extracts from U. S. EPA, the Bureau of Census, the U. S. Geological Survey, the Nuclear Regulatory Commission, the Department of Transportation, and the Federal Emergency Management Agency and were confirmed by ABC personnel. 
 
 
7.  Planned Changes to Increase Safety 
 
7 Automate the chlorination system controls so that when a ton container is empty, the second chlorina 
tor activates and the active chlorinator switches to the off position.  This would include the installation of vacuum regulators on the ton container gas outlet valve. 
7 Increase the frequency of practice drills to respond to an accidental release of chlorine to three times per year. 
7 Implement the use of SCBA equipment while disconnecting and changing ton containers. 
7 Encourage the local volunteer fire companies to become more familiar with the chlorine system at the treatment plant. 
 
 
 
 
 
Table 1 
Summary of the Worst-Case and Alternate Release Scenarios 
 
                                                                      Worst-Case Release                Alternate Release 
 
Type of Accidental Release                               Rupture of ton-container              Shearing of 3/8" copper tubing 
Quantity of Chlorine Released                            2,000 pounds                             1,260 pounds 
Duration of Chlorine Release                              10 minutes        
                         60 minutes 
Rate of Release of Chlorine Gas                         200 pounds per minute                21 pounds per minute 
Wind Speed                                                      1.0 meters/second (3.36 mph)     3.0 meters/second (6.7 mph) 
Atmospheric Stability Class                                F (very stable)                           D (neutral) 
Method used to determine toxic endpoint             RMP*Comp                               RMP*Comp 
Chlorine concentration at the endpoint                 3 parts per million (ppm)             3 parts per million (ppm) 
Radial distance to the toxic endpoint                   1.3 miles (6,900 feet)                  0.1 miles (528 feet) 
Estimated population within radial distance          3,630                                        95 
Number of residences                                        1,550                                        45 
Number of hospitals                                           0    
                                           0 
Number of schools                                             3                                               0
Click to return to beginning