RMP EXECUTIVE SUMMARY 
 
A.   Accidental Release Prevention and Emergency Response Policies 
 
Texas American Foodservice recognizes management's responsibility in protecting its employees, the public, the environment, equipment, and property.  The safety and health of all personnel are very important.  The control of accidents has been and will continue to be a basic responsibility of all personnel in the Fort Worth facility. 
 
 
The facility has  developed and implemented accidental release prevention and emergency response programs which are designed to comply with OSHA's Process Safety Management (PSM) standard (Process Safety Management of Highly Hazardous Chemicals, 29 CFR 1910.119), and EPA's Risk Management Program (RM program) regulation (Risk Management Programs for Chemical Accidental Release Prevention, 40 CFR Part 68).  Mr.Lou Ciferni, Plant Manager, is responsible for implementation of the Risk Management Program. 
 
The purpose of the accidental release prevention and emergency 
response programs is to prevent the occurrence, and minimize the consequences of significant releases of toxic substances as well as fires, explosions, and other types of catastrophic accidents.  Overall, these programs help prevent accidental fatalities, injuries and illnesses environmental impacts and physical property damage. 
 
The accidental release prevention and emergency response programs help prevent accidents because they focus on the rules, procedures, and practices which govern individual processes, activities, or pieces of equipment.  These rules are detailed and improved as necessary.  They are also communicated to and accepted by all employees at the facility. 
 
In addition to the PSM and RM programs, the facility follows these guidelines.  
Safety Management Guidlines 
Safety Committee 
Accident Investigation Committee 
 
 
B.   Stationary Source and Regulated Substances Handled 
 
Texas American Food Service manufactures ground beef.  The facility operates an ammonia refrigerati 
on system to provide cooling and freezing capabilities.  The amount of anhydrous ammonia (CAS #7662-41-7) contained in the system is in excess of 10,000 pounds.  The maximum inventory in the system is approximately 22,000 pounds.  Since an ammonia release from the system could pose a risk of offsite public and/or environmental impact and the system is regulated under the OSHA PSM standard (29 CFR 1910.119), the system is subject to the Program 3 requirements of the EPA's RM program. 
 
 
C.   Summary of Worst-Case and Alternative Release Scenarios 
 
The worst-case release scenario at the Fort Worth facility involves the release of 10,000 pounds of ammonia over a 10 minute period due to the failure of the Pressure Recirculator.  This quantity represents the maximum quantity of ammonia in the recirculator at any time.  Under worst-case weather conditions, ammonia could travel 1.2 miles before dispersing enough to no longer pose a hazard to the public. This distance has been calculated based  
on the method provided in EPA's Risk Management Program (40 CFR 68) Guidance for Ammonia Refrigeration. 
 
The worst-case release scenario is unlikely for the following reasons: 
 
        The worst-case weather conditions which were used for this scenario are not typical; 
        Industry standards were followed for the manufacture and quality control of the receiver;  
        Ammonia is not corrosive in this service; 
        An ammonia detector is located near the recirculator; 
        The facility has a preventive maintenance program in place to maintain the on-going integrity of vessels;  
        The facility has a training program designed to ensure that the system is operated by qualified personnel; and, 
        The facility emergency response procedures enable trained personnel to respond quickly to isolate any potential releases. 
 
The alternative release scenario at the facility involves the release of 3600 pounds of ammonia over a 60 minute period through a defective pressure safety valve (PSV) on the control press 
ure receiver , which lifts to relieve high system pressure but fails to reseat properly.  Under alternative release weather conditions, ammonia could travel 0.1 miles before dispersing enough to no longer pose a hazard to the public.  This distance has been calculated based on the method provided in EPA's Risk Management Program (40 CFR 68) Guidance for Ammonia Refrigeration. 
 
The alternative release scenario is unlikely for the following reasons: 
 
        Industry standards were followed for the manufacture and quality control of the receiver; 
        Ammonia is not corrosive in this service; 
        The facility has a preventive maintenance program in place to maintain the on-going integrity of the receivers; 
        The facility has a training program designed to ensure that the system is operated by qualified personnel; and, 
        The facility emergency response procedures enable trained personnel to respond quickly to isolate potential releases from any leaking equipment. 
 
D.   Description of the Accide 
ntal Release Prevention Program 
 
The prevention program consists of the following elements: 
 
        Employee Participation: This program involves the employees in establishing and implementing the program.  Employees are also to be involved when a process hazard analysis is conducted.  The program also ensures that all employees have complete access to the program. 
 
        Process Safety Information: Written information has been collected which enables the employees to identify and understand the potential hazards in the system. The written information includes the ammonia MSDS and a description of the design of the ammonia refrigeration system. 
 
        Process Hazard Analysis: Formal studies using the What-If/Checklist  Technique have been conducted to examine the system and identify potential hazards. Any recommendations are resolved to improve facility safety.  
 
        Operating Procedures:  Written, detailed procedures have been developed which describe the steps which should be followed to safely 
operate the ammonia refrigeration system. 
 
        Training: A training program has been developed which ensures that employees are trained on all aspects of the system and on the duties which they should perform to ensure the safe operation of the ammonia refrigeration system. 
 
        Contractors: All contractors are screened and evaluated before they perform work on or near the ammonia refrigeration system.  The contractors are also periodically evaluated to ensure that they perform work by following safe work practices. 
 
        Pre-Startup Safety Review: A pre-startup safety review is required  for all new ammonia projects to verify that all safety programs are in place, training has been performed, and construction has been completed according to design standards before the project is put into use. They are also performed when there is a change in the  process safety information 
    
        Mechanical Integrity:  This program ensures that the ammonia refrigeration systems are built and maintained usi 
ng preventive maintenance procedures to minimize unexpected breakdowns or failures. 
 
        Hot Work Permit: These procedures ensure that a signed permit is obtained prior to any cutting, welding, or burning. 
 
        Management of Change: Procedures are designed to ensure that all changes made to the ammonia refrigeration system are properly reviewed. 
 
        Incident Investigation: Procedures ensure that any incidents (and near misses) are investigated, reviewed, and documented using an investigation team. Any recommendations are resolved to improve the safety of the facility.  
 
        Compliance Audits: There are procedures to conduct regular audits of the RM prevention program to ensure that the program is in place and working properly.  Any recommendations from audits are resolved to improve the RM program.  
 
E.   Five-Year Accident History 
 
There have been no ammonia-related incidents at the facility within the last five years that have resulted in onsite or offsite impacts. 
 
 
F.   Description of 
the Emergency Response Program 
 
An emergency response program has been implemented at the  facility.  This program contains procedures describing how the facility will respond to ammonia spills and other emergencies, including evacuation procedures.   
 
The emergency response program consists of the following elements: 
 
        Organization Plan and Responsibilities 
        Communications Procedures 
        Detailed Action Plans 
        First Aid Procedures 
        Emergency Medical Treatment Procedures 
        Evacuation Plans 
        Description of Outside Assistance Available 
        Site Re-Entry Procedures 
        Training Programs and Drills 
 
 
G.   Planned Changes to Improve Safety 
 
The following changes are planned to improve safety conditions and  further strengthen the ongoing safety efforts at the facility: 
 
Participation in Safety and Health Achivement Recognition Program (SHARP)