Greeneville Water Treatment Plant - Executive Summary

| Accident History | Chemicals | Emergency Response | Registration | Source | Executive Summary |

                                                                    EXECUTIVE SUMMARY 
                                                   GREENEVILLE WATER TREATMENT PLANT 
 
    The Greeneville Water Treatment Plant is located about one mile outside the corporate limits of the Town of Greeneville at 2815 Buckingham Road.  There are currently seven full time employees working three shifts at the plant.  The water treatment plant has an operator on duty at all times day or night, seven days per week, 52 weeks per year. 
    The water source for the Town of Greeneville is the Nolichuckey River.  The pump house that contains the pumps that are used to transport the raw water to the Greeneville Water Treatment Plant is located at mile 57.2 on the Nolichuckey River.  Water enters the pump house "pumpwell" through sluice gates located in the wall of the pump house.  The sluice gates are the means by which the amount of water entering the pumpwell is regulated.  After entering the sluice gate 
s the water goes through a traveling bar screen where trash and debris are removed.  Once the raw water is in the pumpwell, potassium permanganate is fed into the water to improve taste and control odors.  We are presently feeding approximately 6 pounds of potassium permanganate to treat one million gallons of raw water. 
    The pump house contains three pumps that are used to transport the raw water to the water treatment plant.  The pumping rates of these three pumps are, one at 8 million gallons per day (MGD), one at 10 MGD, and one at 12 MGD.  After leaving the pump(s) the water travels to the raw water reservoir located at Greeneville's Water Treatment Plant through either a 20 inch in diameter or a 24 inch in diameter pipe. 
    The raw water reservoir at the water treatment plant is a large, man-made, pond type structure that holds approximately 32 million gallons of water.  In addition to being used for the presettling of solids out of the water, it is also an emergency backup 
water source.  This means that, if we were to be notified that the river had a contaminant in it, the water treatment plant could, in order to prevent any contaminated water from entering our system, shut off the pumping station at the river to allow the contaminant to clear-up or pass-by, while still being able to meet the water demands of the Town of Greeneville because of the four day supply of water contained in the reservoir. 
    The reservoir has a structure in it known as the "tower" where water can be drawn from the reservoir from any of three different levels.  Water flows from the "tower" into a 24 inch line that allows the water to flow to the flash mix tanks.  In the flash mix tanks chlorine is added (approximately 200 lbs./7.5 MG of water) to prohibit bacteria growth, powdered activated carbon is added (approximately 16 lbs./MG of water) for taste and odor control, and polyaluminum chloride is added (approximately 83 lbs./MG of water) as a coagulant to help any solids in 
the water settle out at a faster rate.  The water then leaves the flash mix tanks by way of a 20 inch and a 30 inch pipe to the mixing basins.  In the mixing basins the chemicals, that were added in the flash mix tanks, are further mixed with the water by a baffling system. 
    The water then flows into the sedimentation basins where the polyaluminum chloride collects the dirt and sand and causes it to settle to the bottom.  These solids are flushed out of the sedimenttation basins twice yearly and placed into one of two holding lagoons.  In the holding lagoons the solids are allowed to continue to settle.  Only one holding lagoon is used each year while the other is drained and having the solids that have accumulated removed.  The water from the sedimentation basins flows over weirs into filters located inside the water treatment plant building.  These filters are designed to remove any sediment that did not settle out in the sedimentation (settling) basins. 
    There are six filte 
rs in the water treatment plant building.  These filters are made up of anthracite coal, sand, and filter gravel.  Each filter is designed to filter up to 2 million gallons of water daily.  Combined this makes the total filtering ability of the water treatment plant 12 MGD. 
    Once filtered, and as the water flows into tanks called "clearwells", chlorine is once again added to destroy any pathogenic organisms, at a rate of approximately 100 pounds per 7.5 MG of water.  In addition, approximately 6 pounds of fluoride is added per each million gallons of water to aid in the development of children's teeth, lime is added for the adjustment of the water's pH at the rate of approximately 20 pounds per million gallons of water, and approximately 16 pounds of zinc orthophosphate is added per million gallons of water to help prevent corrosion in the distribution system.  These clearwells are designed as holding tanks in order that the chlorine will have ample time to destroy any harmful bact 
eria which may be present in the water before allowing the water to enter the distribution system. 
    From the clearwells, the finished water then enters into pumpwells.  Upon entering the pumpwells the water is considered safe for public consumption and is ready to enter the distribution system.  The water is pumped into the distribution system by using any one, or any combination of, five different pumps that are located at the water treatment plant.  These pumps are rated as follows: two at 3 MGD, one at 6 MGD, one at 8 MGD, and one at 12 MGD.  These pumps, in addition to pumping water directly to the customers, pump water to storage tanks located in different areas of Greeneville. 
    These tanks, in addition to storage, are used to insure that ample water pressure is provided to the customers and for fire protection.  The Greeneville Water Commission presently has seven water tanks with a combined storage capacity of 7 million gallons of water.  This represents a reserve of 7 m 
illion gallons that would be available, in the event of a main line break, to insure that water service to the Greeneville area would not be interrupted. 
    There is instrumentation located at the water treatment plant to continuously monitor the water for pH levels, turbidity (clarity), chlorine residual, the flow entering the treatment plant as well as the flow leaving the treatment plant, and the water level in each of the seven water storage tanks.  This instrumentation is calibrated on a regular basis by authorized personnel to insure it's accuracy. 
    One of the most important control measures to ensure that the water is being treated efficiently and effectively is the use of laboratory sampling.  Laboratory sampling is extensive, with laboratory tests being performed both on site at the water treatment plant and at qualified, state approved, private laboratories.  The operator on duty runs a turbidity (clarity) test on both the raw and finished water, a chlorine residual tes 
t on the sedimentation tank and the finished water, pH on the raw and finished water, and fluoride on the finished water every four hours, 24 hours per day. 
    Laboratory tests are also preformed for the following parameters as well:  trihalomethanes (Thm's) which are by-products of chlorination caused by chlorine mixing with organic compounds in the water, synthetic organic chemicals (SOC's) to check for any man-made chemicals such as insecticides and pesticides, volatile organic chemicals (VOC's) to check for any man-made chemicals such as paint thinners and fuel products, radionuclides to check for any by-products of the nuclear industry, lead and copper, sodium, and asbestos.  The frequency of these tests are determined by the State of Tennessee, Department of Environment and Conservation. 
    Each month we collect and analyze samples from 40 differnet locations throughout the water treatment plant's distribution system.  These samples are tested for chlorine residual, iron, and 
total chliform.  Although the number of samples required to be caught each month in our distribution system is less, we continue to collect and analyze 40 each month to insure the water quality throughout the entire distribution system.  We do this in order to have a better understanding of what is going on within the distribution system at all times.  A result of measures such as these can be evidenced by the fact that the Greeneville Water Treatment Plant has an average of 98.6 points out of a possible 100 points on all "Sanitary Surveys" that have been performed, by the State Health Department, at our plant since 1986. 
    The minimum amount of chlorine residual in the water that is pumped into the distribution system is between 2.0 and 2.5 mg/l.  This is the minimum that is needed to maintain a chlorine residual of at least 0.2 mg/l at any location in the entire distribution system.  This amount is required by our current Public Water System Identification, "PWSID", Permit.  When 
translated into pounds, approximately 300 pounds is used per day to treat a daily flow of 7.5 million gallons of water. 
    Because the chlorine cylinders which are used at the water treatment plant are located inside the building, we are considered to have passive mitigation.  This means that in the event of a chlorine leak, only approximately 55 percent of the chlorine that leaks out would be able to reach the outside atmosphere. 
    The worst-case release scenario for the Greeneville Water Treatment Plant would be to have a tank rupture and release 2,000 pounds of chlorine.  Because of the mitigation, being inside of an enclosure, only 55 percent or 1,100 pounds of chlorine would be released into the atmopshere.  If this kind of a situation were to happen, the chlorine alarm in the chlorine room would sound and alert the operator on duty.  Once alerted the operator would immediately go to the chlorine room to visually confirm a leak.  If the operator determines that there is a ch 
lorine leak he/she would follow the Greeneville Water Treatment Plant's Emergency Response Plan for the correct action(s) to take. 
    In the event of a worst-case release scenario, everyone within a radius of 0.9 miles of the water treatment plant would need to be evacuated.  This action would be handled by the Emergency Management Agency for the Town of Greeneville and would mean that approximately 500 people would need to be evacuated. 
    The alternative release scenario for a chlorine leak at the water treatment plant would mean a release of 200 pounds or less of chlorine.  Again, because of the mitigation, being inside an enclosure, the amount of actual pounds of chlorine leaked to the outside atmosphere would be 110 pounds or less.  If this situation were to occur, the chlorine alarm in the chlorine room would sound and alert the operator on duty.  Once alerted the operator would immediately go to the chlorine room to visually confirm a chlorine leak.  If the operator determin 
es that there is a chlorine leak, he/she would follow the Greeneville Water Treatment Plant's Emergency Response Plan for the correct action(s) to take. 
    In the event of an alternative release scenario everyone within a radius of 0.2 miles of the water treatment plant would need to be evacuated.  This action would be handled by the Town of Greeneville's Emergency Management Agency and would mean that approximately 50 people would need to be evacuated. 
    The Greeneville Water Treatment Plant complies with the OSHA Process Safety Management rule which outlines the correct procedures to follow for any circumstance that may occur.  The Greeneville Water Treatment Plant has a written Emergency Response Plan as required by the Environmental Protection Agency and is included in the written plans of the Town of Greeneville's Emergency Management Agency.  The personnel at the Water Treatment Plant are trained in the latest and most up-to-date procedures concerning chlorine safety and han 
dling.  This training is updated annually to guarantee that all employees know the correct action(s) to take in any situation that might arise. 
    There has not been a major chlorine gas leak at the Greeneville Water Treatment Plant during the last five years.  Occasionally when hooking up a full container of chlorine a lead washer will not seal properly and when the operator turns the valve on to check for leaks a small amount of chlorine gas will escape.  The amount is so small that it will not trigger the alarm and will not leave the confines of the chlorine room.  When this happens the operator will immediately shut off the valve and replace the lead washer and then recheck for leaks.  When there is no leakage detected the container can be placed into service. 
    The response plan at the Greeneville Water Treatment Plant consists of the following components.  The first is the Emergency Response Plan for the Water Treatment Plant which spells out what action(s) are to be taken i 
n the event of a chlorine leak and who is to take the action(s).  If any leaks are detected we have a two man Emergency Response Team designated to respond.  The two members of the Emergency Response Team will perform any needed repairs while their bachup, which will consist of a two member team from the Greeneville Fire Department are on standby outside the chlorine room.  The Emergency Response Plans are included in the written response plan of the Town of Greeneville's Emergency Management Agency.  Training and drills for all water treatment plant employees are arranged and provided by the Greeneville Water Commission in insure that leaks will not occur, but in the event one should occur, employees would be able to respond to it, both efficiently and safely, to better protect the public.  This training consists of the proper fitting, use, care, and maintenance of respirators and protective clothing that might be needed during a chlorine leak.  This training and drills is both classr 
oom and hands-on, and also involves training in the use of any repair tools that might be needed to repair a faulty chlorine tank.  Public notifications and alert systems will be handled by the Emergency Management Agency. 
    There has never been a reportable leak at the Greeneville Water Treatment Plant.  To help insure the public safety, automatic shut-off valves will be installed on all one ton cylinders, that are in use, at the Greeneville Water Plant.  These valves are battery operated and will automatically shut off the flow of chlorine gas in the event of a pipe rupture.  These preventive measures will aid in insuring that chlorine leaks cannot happen.  In addition, more frequent and up-to-date classroom and hands-on training will be scheduled for all employees involved with chlorine handling or the Emergency Response Plan. 
    In closing we want to point out that there has never been, either a worst-case release scenario or an alternative release scenario, chlorine gas leak  
at the Greeneville Water Treatment Plant.  Furthermore, we are confident that, with these measures, there should be no reportable chlorine gas leaks in the future.
Click to return to beginning