     RISK MANAGEMENT PLAN-EXECUTIVE SUMMART 
 
     1. THE FACILITY POLICY 
 
         THE OWNERS,MANAGEMENT,AND EMPLOYEES OF NUWAY COOPERATIVE ARE 
     COMMITED TO THE PREVENTION  OF ANY ACCIDENTAL RELEASES OF ANHYDROUS 
      AMMONIA. IF AN ACCIDENTAL RELEASE SHOULD OCCUR, THE FACILITY IS PREPARED 
      TO WORK WITH THE LOCAL FIRE COMPANY,OR OTHER AUTHORITIES,TO MITIGATE 
      ANY RELEASE,AND MINIMIZE THE IMPACT OF THE RELEASE TO PEOPLE AND THE 
      ENVIRONMENT. 
 
      2. FACILITY INFORMATION 
 
          THE PRIMARY ACTIVITY AT THE FACILITY IS THE STORAGE AND BLENDING OF 
       FERTILIZERS FOR SALE TO FARMERS. 
 
           ANHYDROUS AMMONIA IS RECEIVED,STORED AND DISTRIBUTED FOR DIRECT 
       APPLICATION. ANHYDROUS AMMONIA IS USED FOR CROP PRODUCTION NUTRIENTS. 
 
           THE MAXIMUM QUANTITY OF AMMONI 
A STORED WOULD BE 204,000 POUNDS. 
       IN OUR 18,000 GALLON STORAGE TANK. THE MAXIMUM QUANTITY HANDLED WOULD 
       BE THE UNLOADING OF A TRUCK HOLDING 40,000 POUNDS. 
 
       3. THE WORST CASE SCENARIO AND THE ALTERNATIVE RELEASE SCENARIO. 
 
            A: THE WORST CASE RELEASE SCENARIO FOR ANHYDROUS AMMONIA WOULD BE  
        THE RELEASE OF THE TOTAL CONTENTS OF A STORAGE TANKRELEASED AS A GAS 
         OVER TEN MINUTES. THE MAXIMUM QUANTITY RELEASED WOULD BE 80,000 POUNDS 
         WHICH REPRESENTS THE VOLUME OF THE STORAGE TANK AT 85 PERCENT CAPACITY 
         AS LIMITED BY DESIGNS STANDARDS. THE DISTANCE TO THE ENDPOINT (POINT OF DISPERSION 
         TO 200 PPM) IS .94 MILES. 
 
         B. THE ALTERNATIVE RELEASE SCENARIO FOR ANHYDROUS AMMONIA BASED ON THE 
         DISTANCE TO THE ENDPOINT IS .78 MILES. 
 
       4. THE ACCIDENTAL RELEASE PREVENTION PROGRAM. 
 
            THE FACILITY HAS IMPLEMENTED THE PROVISIONS OF "SAFETY REQUIREMENTS FOR  
       THE STORAGE AND HANDLING 
OF ANHYDROUS AMMONIA,K-61.1" PUBLISHED BY THE 
       AMERICAN NATIONAL STANDARDS INSTITUTE,INC.AND THE STANDARDS OF THE U.S. 
        OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (OSHA),29 CFR 1910.111, 
         "STORAGE AND HANDLING OF ANHYDROUS AMMONIA". IN ADDITION, MINNESOTA 
       DEPT. OF AG RULES. 
 
        5. THE FIVE YEAR ACCIDENT HISTORY. 
 
            A. THER HAVE BEEN NO ACCIDENTAL RELEASES OF ANHYDROUS AMMONIA IN THE PAST  
         FIVE YEARS THAT: 
                  HAVE CAUSED ANY DEATHS, INJURIES, OR SIGNIFICANT PROPERTY DAMAGE AT THE 
         FACILITY: NOR TO OUR KNOWLEDGE, HAVE RESULTED IN OFFSITE DEATHS,INJURIES, 
         EVACUATIONS,SHELTERING IN PLACE,PROPERTY DAMAGE OR ENVIRONMENTAL DAMAGE. 
 
         6. THE EMERGENCY RESPONSE PROGRAM. 
 
              THE FACILITY HAS : 
 
         A. A WRITTEN EMERGENCY ACTION PLAN, IN ACCORDANCE WITH OSHA STANDARD, 
         29 CFR 1910.38: 
 
         B. PROVIDED STATE AND LOCAL AUTHORITIES THE EMERGENCY PLANNING AND 
 
     COMMUNITY RIGHT TO KNOW INFORMATION AS REQUIRED UNDER SARA TITLE III 
          (EPCRA). 
 
           C. COORDINATED WITH LOCAL EMERGENCY RESPONDERS. 
 
          7. PLANNED CHANGES TO IMPROVE SAFETY. 
 
              SAFETY IMPROVEMENT IS AN ONGOING PROCESS AT THE FACILITY. PERIODIC 
          EVALUATIONS ARE PERFORMED TO ASSESS THE MAINTENANCE OF SAFE CONDITIONS. 
          THERE ARE NO ADDITIONAL SPECIFIC ANHYDROUS AMMONIA SAFETY RECOMMENDATIONS 
          FOR IMPLEMENTATION AT THIS TIME.