   1.0  Accidental Release Prevention and Emergency 
                           Response Policies 
At Texas Fibers, Brenham, Tx. , we are committed to 
operating and maintaining all of our processes (especially 
those using hazardous substances) in a safe and responsible 
manner.  We use a combination of accidental release 
prevention programs and emergency response planning programs 
to help ensure the safety of our employees and the public as 
well as protection of the environment.  This document 
provides a brief overview of the comprehensive risk 
management activities that we have designed and implemented, 
including: 
    A description of our facility and use of substances 
                         regulated 
by EPA's RMP regulation 
A summary of results from our assessment of the potential 
offsite consequences from accidental chemical releases 
An overview of our accidental release prevention programs 
A five-year accident history for accidental re 
leases 
of chemicals regulated by EPA's RMP rule 
An overview of our emergency response program 
An overview of planned improvements at the facility 
                      to help 
prevent accidental chemical releases from occurring 
and adversely affecting our employees, the public, 
and the environment 
The certifications that EPA's RMP rule requires us 
to provide 
The detailed information (called data elements) 
about our risk management program 
 
 
  2.0 Stationary Source and Regulated Substances 
 
Our facility produces flexible polyurethane foam 
using a variety of chemicals and processing 
operations.  The facility is housed in an 
approximately 125,000 sq. ft. building located in an 
industrial area.  The process area is divided into 
 
two areas; one being the process building, which 
 
houses the tank farm, which is diked, and the process 
 
area located in the upper half of the process 
 
building.  In our processes, we use the following 
 
chemicals that EPA has identif 
ied as having the 
 
potential to cause significant offsite consequences 
 
in the event of a substantial accidental release: 
 
Toxics: 
 
See Appendix E, MSDS for Toluene Diisocyanate. 
 
Flammables 
 
None. 
 
Our accidental release prevention programs and our 
contingency planning efforts help us effectively 
manage the hazards that are posed to our employees, 
the public, and the environment by our use of these 
chemicals. 
 
 
 
 
 
 
  3.0 Key offsite Consequence Analysis Scenarios 
 
EPA's RMP rule requires that we provide information 
about the worst-case release scenario(s) and 
alternative release scenario(s) for our facility. 
The following are brief summaries of these scenarios, 
including information about the key 
administrative controls and mitigation measures to 
limit the exposure distances for each scenario: 
Worst-case Release Scenario(s) - Regulated Toxic 
Chemicals 
See  Appendix A, for Worst-case Release Scenario. 
The scenario is a rail car failure dumping the entire 
cont 
ents of the car. This scenario has the 
possibility of impacting the small residential 
population around the facility.  Diagrams, and 
modeling information used to develop the Worst-case 
scenario is located in our written program.. 
Alternative Release Scenario(s) - Regulated Toxic 
Chemicals 
For an alternative release scenario we used a line 
                    break. The 
modeling scenario indicated that there are no public 
 
or environmental receptors. The modeling information 
 
is located in appendix a of the written program. 
 
Worst-case Release Scenario(s) - Regulated Flammable 
 
Chemicals None. 
 
Alternative Release Scenario(s) - Regulated Flammable 
 
Chemicals None. 
 
We are using this information to help us ensure that 
our emergency response plan and the community 
emergency response plan address all reasonable 
contingency cases. 
 
 
 
 
4.0 General Accidental Release Prevention Program 
                   and Chemical Specific Prevention 
                   Steps 
 
We ta 
ke a systematic, proactive approach to 
preventing accidental releases of hazardous 
chemicals.  Our management systems address each of 
the key features of successful prevention programs 
including: 
 
Process hazard assessment 
Process hazard review 
Operating procedures 
Training 
Mechanical integrity 
Compliance audits 
Incident investigation 
Employee participation 
Hot work permit 
Contractors 
 
The key to preventing accidental chemical releases 
are the Standard Operating Procedures that are in 
Appendix D. 
 
These individual elements of our prevention program 
work together to prevent accidental chemical 
releases.  Our company and our employees are 
committed to the standard that these management 
systems set for the way we do business, and we have 
specific accountabilities and controls to ensure that 
we are meeting our own high standards for accident 
prevention. 
 
          5.0 Five-Year Accident History 
 
We keep records for all significant accidental 
chemical re 
leases that occur at our facility.  The 
following is a brief summary of accidental chemical 
releases involving materials covered under 
EPA's RMP rule during the past five years: 
 
There have been no accidental releases of TDI in the 
past 5 years. 
 
          6.0 Emergency Response Program 
 
We maintain an integrated contingency plan, which 
consolidates all of the various federal, state, and 
local regulatory requirements for emergency response 
planning.  Our program provides the essential 
planning and training for effectively protecting 
workers, the public, and the environment during 
emergency situations.  Furthermore, we coordinate our 
plan with the community emergency response plan. 
 
      7.0  Planned Changes to Improve Safety 
 
 
The following is a list of improvements that we are 
planning to implement at the facility to help prevent 
and/or better respond to accidental chemical 
releases: 
 
1.  Additional two-w 
ay radios to improve 
communications during operations. 
2,  Fixed monitors. 
3.  High level alarms. 
 
 
                8.0 Certifications 
 
Based on the criteria in 40 CFR 68.10, our Risk 
Management Program is written to comply with Program 
level two.  The distance to the specified endpoint 
for the worst-case accidental release scenario for 
the covered process may impact the small residential 
population surrounding the facility. 
 
Within the past five years, the process has had no 
accidental releases that caused offsite impacts 
provided in the RMP rule (40 CFR 68.10(b)(1)).  We 
have taken voluntary measures to improve our 
operations to minimize potential releases of covered 
materials in order to protect both our employees and 
the public. In the event of fire, explosion, or a 
release of a regulated substance from the process, 
entry within the distance to the specified endpoint 
may pose a danger to public emergency responders. 
Therefore, public emergency responders  
should not 
enter this area except as arranged with the emergency 
contact indicated in the RMPlan.  The undersigned 
certifies that, to the best of my knowledge, 
information, and belief, formed after reasonable 
inquiry, the information submitted is true, accurate, 
and complete. 
 
 
Signature_________________________________________ 
 
Title_____________________________________________ 
 
Date_____________________________________________ 
 
 
               9.0 RMP Data Elements 
 
The following pages present additional information 
about our risk management program that EPA's RMP rule 
has asked us to provide. The information is 
categorized as follows: 
 
-    Registration 
-    Offsite 
consequence analysis 
-    Five-year 
accident history 
-    Program 2 
prevention program 
-    Emergency 
response program
Click to return to beginning