West Virginia - American Water Company Weston - Executive Summary

| Accident History | Chemicals | Emergency Response | Registration | Source | Executive Summary |

WEST VIRGINIA-AMERCIAN WATER COMPANY 
WESTON WATER TREATMENT PLANT  
Risk Management Plan Executive Summary 
 
Accidental Release Prevention and Emergency Response Policies 
 
West Virginia-American Water Company's Weston Water Treatment Plant is committed to operating and maintaining all of our processes (especially those using hazardous substances) in a safe and responsible manner. We use a combination of accidental release prevention programs and emergency response planning programs to help ensure the safety of our employees, contractors, and the public, as well as protection of the environment. This document provides a brief overview of the comprehensive risk management activities that we have designed and implemented, including: 
 
A description of our facility and use of substances regulated by the Environmental Protection Agency's (EPA's) risk management program (RMP) regulation 
 
A summary of results from our assessment of the potential off-site consequences from accidental chemical rel 
eases 
 
An overview of our accidental release prevention program 
 
A 5-year accident history for accidental releases of chemicals regulated by EPA's RMP rule  
An overview of  our emergency response program 
An overview of planned improvements at the facility to help prevent accidental chemical releases from occurring and adversely affecting our associates, contractors, the public, and the environment 
 
Weston Water Treatment Plant Regulated Substances 
 
The Weston Water Treatment Plant is a water treatment facility that takes raw river water from the Westfork River in Weston, West Virginia, and treats the river water with chlorine and other chemicals to make potable (drinking) quality water for public distribution and consumption.  Sewage treatment is not a part of plant operations. The plant handles one RMP-regulated toxic substance above the EPA threshold quantity, which is chlorine. No regulated flammable substances are present at the treatment plant 
 
Chlorine is delivered to our plant a 
nd stored in 1-ton ("ton") containers and is fed to the process from one of the containers at a time. The container storage room can hold up to 4 ton containers. One container is connected to the same feed piping manifold. An alternate supply arrangement consists of one additional ton containers connected to a parallel, but normally isolated, feed piping manifold. Chlorine is stored as a liquefied gas under pressure, fed as a gas to the chlorinators, and injected as a vapor at the outlet of the into the water stream. The chlorine process is classified as a Program Level 3 process, and we implement a complete accident prevention program. 
 
Offsite Consequence Analysis 
 
We performed an off-site consequence analysis to estimate the potential for an accidental release of chlorine from our facility as a regulated toxic substance that could affect the public or the environment. The off-site consequence analysis consisted of evaluating both a worst-case scenario (WCS) and an alternative releas 
e scenario (ARS) following identification of the appropriate ARS. We do not expect a worst-case release scenario to ever occur. An ARS represents a release that might occur during the lifetime of a facility similar to our water treatment plant. ARS's can be used to help the Lewis/Upshur (local) Emergency Planning Committee (L/UEPC) improve and prepare an effective community emergency response plan. 
 
We have submitted release scenario analyses to EPA and have shared that information with L/UEPC and other organizations involved in emergency response activities. It is also available to local residents, schools, hospitals, and businesses. For these events, we have emergency mitigation systems that should help reduce the consequences of the events if they occur. In all cases, if such events occur, we would activate our emergency response plan to respond to the event notify local authorities, and take appropriate actions to protect our employees, contractors, and people in the community. The 
paragraphs below briefly describe the scenarios we have included in our risk management plan (RMPlan), including information about the key administrative controls and mitigation measures we have put in place to limit the exposure distances for each scenario. 
 
Worst-case Release Scenario for Chlorine 
 
The worst case scenario at our water treatment facility involves a failure of a ton container holding approximately 2000 lbs of liquefied chlorine gas under pressure, resulting in a release with vaporization of the entire contents of the container. In this scenario, the chlorine is released as a vaporizing liquid inside a completely enclosed chlorine storage room in our water treatment building. The containment provided by the building mitigates the release. Such building confinement reduces the release rate of chlorine vapor directly to the outdoors. Since this facility is located in a semi-populated area, the toxic cloud formed by the evaporating chlorine would reach off-site end points 
and nearby public receptors. 
 
A sump is provided to collect and contain portions of a liquid release that do not immediately vaporize. In reality, the sump could serve to reduce the vaporization rate of chlorine to the storage room air, and likewise reduce the rate at which chlorine gas is released from the room directly to the outside air. However, because we based our analysis on a very conservative approach, we did not take credit for the sump as a form of mitigation in reducing the endpoint distance reached off-site. 
 
Numerous administrative controls are in place to prevent a release of this type and should one occur, to provide for effective emergency response. Controls include container design, storage, operation, maintenance and inspection; container repair and emergency response equipment; and personnel training conducted in accordance with regulatory requirements, chlorine industry standards and practices, and our company's corporate policies and procedures, which are strictl 
y enforced at the water treatment plant. 
 
 
Alternative Release Scenario for Chlorine 
 
Our alternative release scenario for chlorine involves a chlorine release of approximately 317 lbs through the vent line, should a vacuum regulator failure occur. Credit is taken in accordance with EPA's simplified approach for the partial containment of chlorine vapor by the room/building enclosure, which mitigates the release, and also by conservatively figuring the vacuum feed system to fail at a point during a leak. The building confinement reduces the release rate of chlorine vapor directly to the outdoors. Since this facility is located in a semi- populated area, the toxic cloud formed by the evaporating chlorine would reach off-site end points and nearby public receptors. 
 
As in the WCS, we have taken a very conservative approach to determining the ARS endpoint distance off-site. In determining the ARS endpoint distance we have, in this case, taken credit for active mitigation provided by engin 
eered safeguards that include chlorine monitors/detectors that automatically activate an alarm in the control room and the vacuum feed system. The chlorine leak detection system is calibrated to initiate alarms at very low concentrations of chlorine (i.e., lower than industry recommended settings). Some of our additional engineering safeguards are outlined in the following section of this summary and include isolation valves. Isolation valves are provided in the downstream chlorine feed system to isolate downstream chlorine source from the pigtail leak.  As stated in the description of the WCS, numerous administrative controls are in place to prevent a release of this type and to provide effective emergency response should one occur. 
 
We are using this information to help us ensure that our site/facility emergency response plan and the community emergency response plan address all reasonable contingency cases. 
 
Accidental Release Prevention Program and Chemical-specific Prevention Step 
s for Chlorine 
 
We take a systematic, proactive approach to preventing accidental releases of hazardous chemicals. Our RMP-regulated chlorine process is also subject to the Occupational Safety and Health Administration's (OSHA's) process safety management (PSM) standard. We have extended the PSM program at this facility, where necessary, to satisfy EPA's Program Level 3 accident prevention program requirements. Our PSM Program and RMP Level 3 Prevention Program are designed to comply with OSHA and EPA requirements.  Additionally, we adhere to chlorine industry    (i.e.., Chlorine Institute) and American Water Works Association guidance and recommended practices for PSM and RMP programs, including facility and chlorine system design and safety practices. 
 
Our accidental release prevention programs and our contingency planning efforts help us effectively manage the hazards that are posed to our employees, contractors, the public, and the environment by our use of chlorine in treating drinki 
ng-quality water. We are using this information to help us ensure that our emergency response plan and the community emergency response plan address all reasonable contingency cases. Our systematic, proactive management systems address each of the key features of successful prevention programs including: 
 
Process safety information 
Process hazard analysis 
Operating procedures 
Training 
Mechanical integrity 
Management of change 
Pre-startup review 
Compliance audits 
Incident investigation 
' Employee participation 
Hot work permit 
Contractors 
 
As part of our prevention efforts, the following is a list of key safeguards and chlorine-specific accidental release prevention steps that we have implemented at our site: 
 
A new, state-of-the-art chlorine feed system 
 
Instrumentation and control systems with an emergency power supply designed in accordance with current industry (recognized and generally accepted good engineering) practices 
 
Corrosion-resistant equipment components and pipi 
ng systems 
 
Protective devices to prevent the formation of excessive pressure in chlorine equipment 
 
Isolation valves to permit isolation of different parts of the process 
 
Chlorine monitors/detectors with alarm notification to a constantly attended control room and to other key facility locations 
 
A liquid chlorine spill collection and containment system consisting of floor drains 
Chlorine rooms designed to help contain a chlorine release, and building construction materials that will not support fire development, fire spread, and fire damage to equipment 
 
Strict administrative controls prohibiting the entry and use of combustible materials in chlorine handling/use areas to prevent and control fire spread that may pressurize equipment 
 
Cross-trained operations and maintenance personnel that are equally trained in emergency response actions for chlorine releases to the OSHA (29 CFR1910.120) EPA HAZWOPER responder level 
 
These individual elements of our prevention program work together  
and in tandem with the chlorine release prevention steps to prevent accidental chemical releases. Our company, our employees, and contractors are committed to the standard that these management systems set for the way we do business, and we have specific, internal management accountabilities and controls to ensure that we are meeting our own high standards for accident prevention. 
 
Five-year Accident History 
 
We keep records for all significant accidental chemical releases that occur at our facility.  During the past 5 years we have not had any releases involving chlorine from the RMP-covered process that had any reportable on-site or off-site effects.  Our facility has instituted procedures that require formal investigation of incidents involving chemical releases, regardless of chemical identity or listing by the EPA RMP rule. For each incident, we conduct formal incident investigations to identify and correct the root causes of the events. 
 
Emergency Response Program 
 
The West Virgi 
nia-American Water Company's Weston Water Treatment Plant maintains an integrated contingency plan, which consolidates all of the various federal, state, and local regulatory requirements for emergency response planning. Our program provides the essential planning and training for effectively protecting workers, contractors, the public, and the environment during emergency situations. The program consists of procedures for responding to a chlorine release. The procedures address all aspects of emergency response, including (1) proper first aid and emergency medical treatment for human exposures, (2) facility evacuation plans and accounting for facility personnel after an evacuation, (3) notification of local emergency response agencies and the public if a release occurs, and (4) post-incident follow-up requirements. Procedures are in place governing the establishment of the plant's Emergency Operation Center where management personnel can direct and control emergency operations on an a 
s-needed basis. 
 
In addition, we have procedures that address maintenance, inspection, and testing of emergency response equipment, as well as instructions that address the use of emergency response equipment. Employees receive training in these procedures to perform their specific emergency response duties. The emergency response program is updated when necessary based on modifications made to plant facilities or to the chlorine storage and feed process, or when improvement benefits are recognized. Affected personnel are informed about, and trained on, the changes, 
 
The overall emergency response program for the plant is coordinated with the local emergency planning committee (LEPC) having jurisdiction in Lewis and Upshur Counties - and with Lewis County and Weston, West Virginia, emergency management officials. We have around-the-clock communications capability with appropriate emergency response organizations (e.g.., contracted chlorine emergency response [HAZMAT] teams, local fire  
department, police department). This provides a means for notifying the public of an incident, if necessary, as well as facilitating quick response to an incident. Additionally, we conduct periodic walk-around orientation tours of the plant facilities with key representatives of local emergency response organizations. During such tours we discuss and review the source of chlorine at our site, the hazards of a chlorine release, release mitigation features and emergency response actions involving the chlorine system.  Thus, our emergency response plan is fully coordinated with the community emergency response plan. 
 
Planned Changes to Improve Safety 
 
At the West Virginia-American Water Company Weston Water Treatment Plant we constantly strive to improve the safety of our operations through periodic safety reviews, our incident investigation program, and a program for soliciting safety suggestions from our facility workers. We resolve all findings from our reviews of proposed changes to f 
acilities, equipment, and operations and from analyses of process hazards. Some findings of this type can result in modifications to the process. the prevention program, or administrative controls. The following is a list of improvements that we are planning to implement at the facility during the next 5 years to help prevent and/or better respond to accidental chemical releases: 
 
An engineering review of the leak-tightness of each chlorine room to more precisely determine the building (containment) mitigation factor, possibly resulting in reduced endpoint distances for WCS and ARS releases of chlorine 
 
An assessment of the effectiveness of each element of the Level 3 Prevention Program to ensure that the program will achieve its objectives and to strive for continuous program improvement
Click to return to beginning