Travis County MUD #4 Water Treatment Plant - Executive Summary

| Accident History | Chemicals | Emergency Response | Registration | Source | Executive Summary |

                      Executive Summary 
 
 
0.1    Owner/Operator 
 
This site is owned by Travis County Municipal Utility District No. 4.  It is operated by ECO 
Resources, which is subject to the requirements of OSHA 1910.120.  Therefore, this is a 
Program 3 Risk Management Plan submittal.  It is the policy of the MUD and ECO resources 
to fully comply with OSHA and Environmental Protection Agency (EPA) regulations 
regarding the storage and use of hazardous materials. 
 
0.2      Description of the Stationary Source and Regulated Substances Handled 
 
0.2.1    Stationary Source Description 
 
This source is a 3.0 million gallon per day municipal utility district water treatment (water 
supply) plant that provides potable water for the Barton Creek Subdivision.  One of the 
components of the treatment plant is disinfection of the water by chlorination.  This site is 
located in an area where the terrain consists of relatively steep hills. 
 
0.2.2    Regulated Substances 
 
The only regulated substance presen 
t at this facility is chlorine gas, which is delivered in one 
ton cylinders. 
 
0.3    Release Scenarios 
 
0.3.1    Worst-case Release Scenario 
 
The worst-case release scenario for this site is the rapid loss (complete loss over a ten-minute 
period) of a full 2,000-pound chlorine cylinder.  The distance to the endpoint for this 
scenario is 1.3 miles.  A 1.3-mile radius around this site encompasses 1,219 homes and 
apartments, including existing structures, structures under construction and planned structures 
under development (estimated population 3,700); a recreation area (golf course and country 
club); and schools. 
 
0.3.2    Alternative Release Scenario 
 
The alternative release scenario assumes a full leak at the 3/4 inch cylinder vapor connection.  
This scenario generates a chlorine gas release rate of 86 pounds (of chlorine) per minute.  
The predicted distance to the endpoint is 0.2 miles.  Public and environmental receptors 
within this distance include 64 homes (estimated population 190). 
 
 
0. 
3.3    Administrative Controls and Mitigative Measures 
 
No engineered passive controls are in place for a chlorine release from this site.  Active 
controls consist of chlorine gas monitors near the chlorine gas system that provide direct 
chlorine readings at the site and sound alarms at the ECO Resources (operator) building.  
ECO Resources has  emergency equipment and a leak repair kit.  A SCBA is kept at the facility 
for use by personnel responding to a leak.  There are emergency procedures in place for 
stopping leaks and for notification of local authorities and emergency response teams.  
 
0.4    Five-year Accident History 
 
There have been no accidents or releases at this site over the past five years (or ever) that have 
resulted in any injuries or property damage. 
 
0.5    Emergency Response Program 
 
Upon discovery of a leak by an employee or local resident report or via the chlorine gas 
monitor/alarm system, ECO Resources notifies the local chlorine response team and the 
facility operator.   
On-site response time is 30 minutes or less.  If the response team determines 
that 10 pounds of chlorine have been released, or if there is a potential health or off-site 
health threat, the proper authorities are notified immediately.  These include the Travis 
County Office of Emergency Management, City of Austin Office of Emergency Management, 
the NRC, the TNRCC and, if necessary, 911 for fire and police assistance.  The response 
team will also take immediate steps to shutdown the system and stop/repair the source of the 
release. 
 
0.6    Changes to Improve Safety 
 
No changes to improve the safety of this site are currently pending or being implemented.  
There are no recommended changes at this time.