Cosme Water Treatment Plant - Executive Summary

| Accident History | Chemicals | Emergency Response | Registration | Source | Executive Summary |

EXECUTIVE SUMMARY 
City of St. Petersburg Water Treatment Facilities 
 
Introduction and Background 
 
The USEPA's Clean Air Act Amendments of 1990 included provisions that require facilities that use certain substances to develop a plan to reduce the likelihood of an accidental release of the substances to the atmosphere and reduce the likelihood of serious harm to the public and the environment. The plan must also include mitigation measures to reduce the potential impact on the public in the unlikely event of a release. The requirements of this plan, commonly referred to as a Risk Management Plan (RMP), are detailed and codified in 40 CFR Part 68. 
 
The City of St. Petersburg Public Utilities Department, Division of Water Supply consists of three water treatment facilities: the Cosme Water Treatment Plant (WTP), the Oberly Pump Station and the Washington Terrace Pump Station.  These three facilities store chlorine in quantities above the regulatory thresholds at which a RMP/PSM is require 
d. Chlorine is used to disinfect the water prior to distribution. 
 
The RMP/PSM consists of three compliance programs, each with progressively stricter compliance standards. The chlorination process at the water treatment facilities are subject to Program 3, the most stringent of the three programs, because the facilities are subject to the OSHA Process Safety Management (PSM) Standards and a worst-case release of chlorine could affect the public. 
 
The RMP/PSM consists of three major parts. The first part is the Hazard Assessment. The Hazard Assessment is done to determine the effects that a release of a regulated substance could have on the public. The second part is a Prevention Program that consists of 12 elements designed to improve the system safety and decrease the likelihood of a release. The third part is the Emergency Response Program, which develops a plan for dealing with a release in the unlikely event that one would occur. Because the regulations are very similar, the Preve 
ntion Program and the Emergency Response Program also serve as the OSHA PSM plan, and this document is therefore referred to as the RMP/PSM plan. 
 
As part of the RMP, a submittal to the USEPA is required which is referred to as RMP/PSM Submit. 
 
Hazard Assessment 
 
A Hazard Assessment was performed to determine the effects a release would have on the public. For chlorine, the distance a set endpoint concentration of the gas would travel must be determined. In addition, an estimate of the population that could be affected by a release of chlorine was determined and sensitive receptors such as hospitals, schools, and nursing homes were identified. The Hazard Assessment considers two release scenarios-a "worst case" and an "alternative case."  
 
Worst-Case Scenario 
 
The regulations require the development of a worst-case release scenario based on conservative assumptions. For example, it is required to assume that the entire contents of the largest single container of chlorine will be releas 
ed over 10 minutes. For the St. Petersburg facilities, it is assumed that an entire one-ton cylinder of chlorine is released over 10 minutes.  This is unlikely to occur since the properties of chlorine would cause a freeze and thaw cycle to occur at the leak, which would slow the release. In addition, only "passive" mitigation methods such as buildings or dikes can be considered when determining the distance the release could travel. Passive mitigation, as defined, requires no mechanical, electrical, or human input. However, in many scenarios mitigating the release by isolating the process could reduce the amount released. In addition, the worst-case scenario requires that conservative atmospheric conditions be assumed which results in a large area of impact.  
 
The hazard assessment requires that the "toxic endpoint" or distance from the point of release to a location at which the chemical concentration equals or exceeds a certain concentration be determined. That concentration is defi 
ned as the maximum airborne concentration below which individuals could be exposed for up to 1 hour without experiencing or developing irreversible or other serious health effects, or symptoms that could impair an individual's ability to take protective action. Because the cloud from a chlorine leak would disperse relatively quickly, an individual at a toxic endpoint would be exposed to the exposure limit concentration for much less than the 1 hour assumed by the limit. In addition, the exposure limit concentrations result in relatively minor health effects. Therefore, an individual at the toxic endpoint would be affected less than the results of the worst-case scenario may imply. 
 
The model used for the worst-case scenario determined the distance at which the chemical's concentration was 3 ppm or greater (the toxic endpoint for chlorine).  Based upon the model results, the worst-case scenario distance was determined to be 1.09 miles for the Cosme WTP, 1.02 miles for the Oberly Pump St 
ation and 1.01 miles for the Washington Terrace Pump Station. 
 
Alternative Scenario 
 
The RMP rule also requires that at least one alternative release scenario be evaluated for chlorine. The alternative scenarios reflect a type of release that is more likely to occur compared to the worst-case scenario. Unlike the worst-case scenario, the alternative release scenario may consider "active" mitigation such as shutoff valves and a more realistic release quantity and release rate. Active mitigation is defined as requiring mechanical, electrical, or human input. Lastly, it assumes local, typical meteorology, which is more realistic than the conservative meteorological conditions that must be assumed for the worst-case scenario.  
 
Two alternative release scenarios were investigated for chlorine at each of the St. Petersburg facilities.  In the case of the pump stations, the alternative release scenarios for chlorine were a release through a vacuum regulator pressure release valve and a one-to 
n cylinder fusible metal plug rupture.  In the case of the treatment plant, the alternative release scenarios occurred through a flexible connector break and through a corrosion leak in the chlorine gas piping or piping joint.  The alternative release scenario is considered to be more representative of the effects likely in the event of a release.  The results of the alternative release scenarios are presented in Table 1 below. 
 
 
Table 1 City of St. Petersburg Results of Alternative Release Scenarios 
 
Facility/Scenario               Toxic Endpoint (miles) 
 
COSME WTP 
Flexible Connector Failure         0.20 
Corrosion Leak                          0.22 
 
OBERLY PS 
Vacuum Regulator Release     0.20 
Fusible Plug Rupture                0.38 
 
WASHINGTON TERRACE PS 
Vacuum Regulator Release     0.20 
Fusible Plug Rupture                0.39 
 
 
Prevention Program 
 
The Prevention Program, together with the Emergency Response Program and Hazard Assessment, make up the RMP/PSM. The Prevention Program  
consists of 12 elements designed to improve the system safety and decrease the likelihood of a release. 
 
Employee Participation 
 
The participation of the City of St. Petersburg water treatment facility staff in preparing the RMP/PSM program was critical to the program's successful implementation. Employee participation is valuable because it increases the safety awareness of the staff and it allows the staff's experience in operating and maintaining the processes to be incorporated into the plan. 
 
Water treatment facility staff participated in the development of the Prevention Program through a series of meetings and workshops, as well as the Process Hazard Analysis described below. All facility staff received awareness training that instructed staff on how the RMP/PSM requirements may impact their jobs, an overview of each of the RMP/PSM plan elements and the procedures that must be followed to comply with the requirements of the RMP/PSM plan. 
 
Process Safety Information 
 
The RMP regu 
lations require that information concerning process chemicals, technology, and equipment be compiled as part of an RMP program. Emergency response planners can use such information to develop training programs and procedures, or as a general resource. The information will be supplied to contractors who will work in the chlorine process area as part of the requirements outlined in the Contractors element. All the required process safety information was compiled as required by the RMP regulations. The information meets and in many cases exceeds the minimum required by the regulations. 
 
Process Hazard Analysis 
 
A process hazard analysis (PHA) was systematically conducted to evaluate potential causes and consequences of accidental releases. This information was used by water treatment facility staff to improve safety and reduce the consequences of accidental releases. Equipment, instrumentation, utilities, human actions, and external factors that might affect the process were the focus of  
the PHA. 
 
A Process Hazard Analysis team was assembled within the Division of Water Supply. The chlorine PHA was conducted by a team of water treatment facility staff familiar with the process operation and maintenance and facility management. The PHA team has expertise in engineering, chlorine process and operation and chlorine process hazard analysis methodology.  
 
The PHA was done using a combination of "What-If" and "Checklist" methods. Based on the results of the PHA, changes in operating, maintenance, and other process safety management procedures that would improve the overall safety of the water treatment facilities were identified. The changes that most affect the severity and likelihood of a release have been adopted by the facilities and incorporated as part of the overall Process Safety Management Program. Other improvements and process modifications to reduce or eliminate potential hazards are scheduled to be implemented or incorporated. 
 
Operating Procedures 
 
Operating pr 
ocedures for the chlorination process have been developed as part of the RMP/PSM. Written operating procedures assure continuous, efficient, and safe operation of the facility. The goal of the operating procedures is to provide clear instructions to safely operate the process. Operating procedures are also used to train new employees and to provide refresher training for existing staff. 
 
The detailed operating procedures include startup, shutdown and emergency operating procedures. The procedures describe how the system should be operated in order to minimize the chances of an accidental release. The procedures also emphasize safety considerations during operation and address hazardous situations that can occur and how to correct them. 
 
Training 
 
An effective RMP/PSM training program can significantly reduce the number and severity of accidental releases. Employees involved in operating or maintaining the chlorination process must receive training that includes applicable operating and 
maintenance procedures and an overview of the process. Training must emphasize safety and health hazards and safe work practices. 
 
City of St. Petersburg water treatment facility staff have received initial training on the operations and maintenance of the regulated processes through on-the-job training. Staff who operate and maintain the RMP/PSM processes were trained how to safely maintain and operate the processes.  The Division of Water Supply certifies each of the Water Plant Operators and Maintenance personnel on the safe handling of chlorine and emergency response annually through the Chlorine Responder Certification Program.  The Public Utilities Department, Office of Training and Safety gives annual training on equipment lock-out/tag-out procedures, confined space entry procedures and hot work permit procedures.   
 
Contractors 
 
The City's water treatment facilities must make contractors aware of the known hazards of the chlorine process related to the contractors' work. In ad 
dition, the water treatment facilities must make contractors aware of the applicable elements of its emergency response plan. The City should screen for contractors that can perform work on or adjacent to the chlorine process without compromising the safety and health of employees at the facility.  
 
The City must obtain and evaluate information regarding the contractor's safety performance and programs before allowing a contractor to work on or adjacent to the chlorine process. When a contract involving work on or adjacent to the chlorine process is to be bid, the bidding procedures must ensure that contractor safety management requirements are met.  To make the contractor aware of the water treatment facilities RMP/PSM plan requirements, a safety briefing must be conducted before work begins in or adjacent to any covered process. Upon arriving at the facility for the first time to perform work, the contractor will be presented a Contractor Safety Management Briefing Form that must be  
read and signed.  
 
Pre-startup Review 
 
A pre-startup safety review must be conducted for any new covered process or for significant modifications to the existing chlorine process that necessitate a change in the process safety information. No new or significantly modified process will start up and no acutely hazardous chemicals will be introduced into such a process prior to the pre-startup safety review. The purpose of the pre-startup safety review is to ensure that the facility is ready to operate new and modified regulated processes safely.  
 
To initiate the pre-startup safety review, all updated elements of the Process Safety Management Plan are assembled for review. This includes all process safety information, process hazard analysis, operating procedures, employee training and mechanical integrity records. The pre-startup safety review team should complete and sign a Pre-startup Safety Review Form. This form documents the process, and helps ensure that the review has been proper 
ly performed. The Pre-startup Safety Review Form must be authorized before startup. 
 
Mechanical Integrity 
 
An effective mechanical integrity program is one of the primary lines of defense against a release. The mechanical integrity program addresses equipment testing and inspection, preventive maintenance schedules, and personnel training. The intent is to ensure that equipment used to process, store, or handle chlorine is maintained and installed to minimize the risk of releases. 
 
The City's water treatment facility maintenance staff has a mechanical integrity program that includes equipment and instrumentation identification, maintenance, testing and inspection schedules, personnel training and maintenance documentation. Preventive maintenance is scheduled based on equipment manufacturers' recommendations published in their operation and maintenance (O&M) manuals.  In addition to preventive maintenance, water treatment facility staff performs corrective maintenance in the event of eq 
uipment malfunction or breakdown. Work orders indicate what safety precautions must be followed including whether lockout/tagout or confined space entry provisions are applicable.  
 
Hot Work Permits 
 
RMP/PSM regulations require employees and contractors to employ safe work practices when performing "hot work" in, on, or around the chlorine process. To ensure that hot work is done safely, a Hot Work Permit Program has been developed that requires a permit to be issued before hot work is performed. Examples of such work include but are not limited to: welding, cutting, grinding, brazing and operating flame- or spark-producing operations. 
 
The hot work permit requires the identification of hazards and appropriate safeguards, as well as the implementation of the safeguards to ensure a fire-safe workplace.  
 
Management of Change 
 
A system for the proper management of changes and modifications to equipment, procedures, chemicals, and processing conditions is required under the RMP/PSM. Modif 
ications to the chlorine system will be reviewed before they are implemented to determine if the modification would compromise system safety. An effective change management system will help minimize the chance for an accidental release. 
 
If a modification covered under RMP/PSM is made, its effects must be addressed, employees must be informed, and the written procedures must be updated. The intent is to require that all modifications to equipment, procedures, and processing conditions other than "replacement in kind" be managed by identifying and reviewing them before implementation. A Management of Change Evaluation Form will be completed and evaluated for any modifications that are covered under the RMP/PSM. The Management of Change Form will be evaluated by the Chief Water Plant Operator who will authorize the change prior to its initiation.  A Notification of Process Change Checklist is also completed prior to system modification. 
 
Incident Investigation 
 
Each incident that resulte 
d in or could reasonably have resulted in a catastrophic release (i.e. a release that results in death or permanent injury) of chlorine must be investigated. A process to identify the underlying causes of incidents and to implement procedures for preventing similar events has been developed. To investigate an incident, an Incident Investigation Review Committee will be established. As part of the investigation, an Incident Report Form will be prepared to recommend system changes. 
 
The investigation team should ask questions such as what equipment failed, which behavior failed, and which material leaked, reacted, or exploded? As part of the incident review, staff actions that may have contributed to the incident will also be reviewed. A determination will be made as to whether it is necessary to institute additional training for the employees to prevent the incident from occurring in the future. On the Incident Report Form, the Chief Water Plant Operator identifies which of the recommen 
ded system changes are approved for implementation. The incident investigation report and any changes resulting from the report will be reviewed with all staff members who operate and maintain the applicable system.  
 
Compliance Audit 
 
The City of St. Petersburg's water treatment facilities are required to complete a compliance audit for the RMP/PSM program. The primary goals of conducting an internal compliance audit are to gather sufficient data to verify compliance with RMP/PSM requirements and good process safety practices, identify process safety deficiencies and develop corrective actions, and increase safety awareness among facility staff. 
 
The compliance audit methodology is modeled after OSHA's guidelines for conducting regulatory PSM compliance audits: Compliance Guidelines and Enforcement Procedures, OSHA Instruction CPL 2-2.45A (September 28, 1995). An internal compliance audit must be conducted at the facility at least once every 3 years for the chlorine process. A team th 
at includes at least one person knowledgeable in the covered processes and an audit leader knowledgeable in RMP/PSM requirements and audit techniques will conduct the audits. The Chief Water Plant Operator and the audit team will promptly determine an appropriate corrective action for each deficiency identified during the audit and document the corrective actions and the dates by which they must be taken. 
 
Emergency Response Program 
 
The Emergency Response Program develops a plan for dealing with a chlorine release. OSHA Process Safety Management regulation 29 CFR 1910.119(n) and EPA RMP regulation 40 CFR 68 Subpart E require that an Accidental Release Emergency Response Plan be prepared. The plan must be prepared in accordance with the provisions of another overlapping OSHA regulation-Employee Emergency Plans (29 CFR 1910.38(a)). In addition, provisions of the OSHA hazardous waste and emergency response standard, 29 CFR 1910.120 (q), must also be considered. The Emergency Planning and 
Response Plan described in this section complies with the requirements of 40 CFR 68.95, 29 CFR 1910.38(a), and 29 CFR 1910.120(q).  
 
An Emergency Planning and Response Plan must be developed that provides employees with guidance on how to protect public health and the environment in case of a chemical discharge emergency.  The emergency response procedures cover a release from the initial alarm stage through either leak stoppage or hazmat assistance. As part of the emergency response procedures there are plans for victim rescue, leak investigation, and communication with additional support agencies. In addition, critical facility operations are identified to insure that, if possible, the critical water treatment facility functions are kept operational. The Emergency Planning and Response Plan also indicates the level of training needed to complete the emergency response procedures.  
 
Information regarding self-contained breathing apparatus is also provided in the plan. It also address 
es facility site communication, emergency response equipment, first aid and medical treatment, medical surveillance and consultation, and emergency response drills. 
 
The City has developed a comprehensive Emergency Response Program that fully satisfies RMP/PSM requirements. The procedures are outlined in the Public Utilities Department Safety Rule 2.06, Chlorine Handling Procedures (Emergency Notification and Evacuation).  According to the ERP, all water treatment facility personnel are HAZMAT trained in order to function as first responders in the event of a chlorine release. Pinellas and Hillsborough County HAZMAT teams will also be called upon to assist. However, at the Oberly Pumping Station, personnel (normally operated with one employee) will only respond to accidental releases of 10 pounds of chlorine or less. In the event of a larger release, personnel will assemble at a designated location for evacuation of the facility after notifying the proper authorities. The same procedur 
es are pertinent to the Washington Terrace Pumping Station, although normally this facility is unmanned. Evacuation of areas surrounding each facility, if necessary, is a responsibility of local police and fire departments.   
 
Summary 
 
The USEPA's Clean Air Act Amendments of 1990 included provisions that require facilities that use certain substances to develop a plan to reduce the likelihood of an accidental release of the substances to the atmosphere and reduce the likelihood of serious harm to the public and the environment.   
 
City of St. Petersburg WTP staff participated in the development of the Prevention Program through a series of meetings and workshops.  All the required process safety information was compiled as required by the RMP regulations. PHA information was used by WTP staff to improve safety and reduce the consequences of an accidental release. Operating procedures for the chlorination process have been developed. Staff have received initial training on the operation 
s and maintenance of the regulated processes.    
 
Additional RMP/PSM plan elements that have been completed include the development of a Contractor Safety Management Briefing Form, Hot Work Permit Program, Management of Change Evaluation Form, Incident Report Form, completion of a compliance audit and the performance of preventive and corrective maintenance.  The City has also developed a comprehensive Emergency Response Program that fully satisfies RMP/PSM requirements.  
 
There were no reportable accidents at the Cosme WTP, Oberly Pump Station and Washington Terrace Pump Station between June 21, 1994, and the present date.
Click to return to beginning