Accident on 1997-04-25 14:15:00
Water Supply and Irrigation Systems (22131) |
00:01:00 |
Release Event
Release Source
Weather Conditions at the Time of Event
On-Site Impacts
Known Off-Site Impacts
Environmental Damage
Initiating Event
Contributing Factors
n |
y |
y |
n |
n |
n |
n |
n |
n |
n |
n |
Contractor failed to remove air from new line being pressure tested (with water only); new line failure caused damaged to adjacent existing solution line resulting in momentary release of solution. |
Off-site Responders Notified
Changes Introduced as a Result of the Accident
n |
n |
n |
n |
n |
n |
n |
n |
n |
n |
Included contractor certification in Risk Management Plan |
Confidention Business Information
Chemicals in Accident History
0.1% of 1 lbs. of the Toxic Chemical "Chlorine", CAS: 7782-50-5.
|