Vastar Resources, Inc. - Grand Chenier Gas Plant - Executive Summary

| Accident History | Chemicals | Emergency Response | Registration | Source | Executive Summary |

25999 LDEQ Facility ID Number 
 
Grand Chenier Gas Plant Risk Management Plan 
Executive Summary 
 
 
 
ACCIDENTAL RELEASE PREVENTION AND RESPONSE POLICIES 
 
Vastar Resources, Inc.s (Vastars) policy is to manage all operations in a manner that  
protects the environment and the health and safety of employees, customers,  
contractors, and the public. This is demonstrated by the resources invested in accident  
prevention, such as training personnel and considering safety in the design, installation,  
operation, and maintenance of our processes. While prevention is our goal, if a release  
does occur, trained personnel will respond to control and contain the release. 
 
DESCRIPTION OF THE STATIONARY SOURCE AND REGULATED SUBSTANCES 
 
Vastars Grand Chenier Gas Plant, located in Grand Chenier, Louisiana, operates a  
variety of processes to extract natural gas liquids from natural gas. The plant has  
hydrocarbon mixtures containing regulated flammable substances including methane,  
ethane, propane, n-b 
utane, iso-butane, n-pentane, and iso-pentane. The plant does not  
have threshold quantities of any regulated toxic substances.  
 
OFFSITE CONSEQUENCE ANALYSIS (OCA) RESULTS 
 
The worst-case scenario (WCS) is failure of a 120,000-gallon storage tank containing  
natural gas liquids (NGL) resulting in a vapor cloud explosion (VCE). Based on the TNT  
equivalency method contained in EPAs RMP Offsite Consequence Analysis Guidance,  
the WCS would impact public receptors. 
 
The alternative release scenario (ARS) is a VCE resulting from the release of 18,400  
gallons of NGL, which is the normal inventory of the 120,000-gallon storage tank. (The  
NGL storage tanks are almost never filled to capacity.) Based on flash formation factors  
from EPAs RMP Offsite Consequence Analysis Guidance and a yield factor of 0.03, the  
ARS would impact public receptors. While vapor cloud explosions are generally  
considered unlikely events, this ARS is more likely than the WCS and satisfies the ARS  
requirement o 
f impacting public receptors. As such, it represents a more practical  
scenario for emergency planning. 
 
GENERAL ACCIDENTAL RELEASE PREVENTION PROGRAM 
 
The following is a summary of the accident prevention program in place at the plant.  
Because processes at the gas plant that are regulated by the Environmental Protection  
Agency's (EPA's) risk management program (RMP) regulation are also subject to the  
Occupational Safety and Health Administration's (OSHA's) process safety management  
(PSM) standard, this summary addresses each of the OSHA PSM elements and  
describes the management system in place to implement the accident prevention  
program. 
 
Employee Participation 
 
The Grand Chenier gas plant encourages employees to participate in all facets of  
process safety management and accident prevention. Examples of employee  
participation range from updating and compiling technical documents and chemical  
information to participating as a member of a process hazard analysis (PHA) team.  

mployees have access to all information created as part of the gas plant accident  
prevention program. Specific ways that employees can be involved in the accident  
prevention program are documented in an employee participation plan that is  
maintained at the gas plant and addresses each accident prevention program element.  
In addition, the gas plant has a number of initiatives under way that address process  
safety and employee safety issues. These initiatives include an area safety committee  
to promote both process and personal safety. The teams typically have members from  
various areas of the plant, including operations and maintenance.  
 
Process Safety Information 
 
The Grand Chenier gas plant  keeps a variety of technical documents that are used to  
help maintain safe operation of the processes. These documents address chemical  
properties and associated hazards, limits for key process parameters and specific  
chemical inventories, and equipment design basis/configuration inform 
ation. The  
Management of Change process insures process safety information is kept up to date.  
Chemical-specific information, including exposure hazards and emergency response/  
exposure treatment considerations, is provided in material safety data sheets (MSDSs). 
 
This information is supplemented by documents that specifically address known  
corrosion concerns and any known hazards associated with the inadvertent mixing of  
chemicals. Plant specific operating procedures contain safety-related limits for specific  
process parameters (e.g., temperature, level, composition). The gas plant ensures that  
the process is maintained within these limits using process controls and monitoring  
instruments, highly trained personnel, and safety systems. 
 
The gas plant also maintains numerous technical documents that provide information  
about the design and construction of process equipment. This information includes  
materials of construction, design pressure and temperature ratings, and electr 
ical rating  
of equipment. This information, in combination with written procedures and trained  
personnel, provides a basis for establishing inspection and maintenance activities, as  
well as for evaluating proposed process and facility changes to ensure that safety  
features in the process are not compromised. 
 
Process Hazard Analysis (PHA) 
 
The Grand Chenier gas plant has a comprehensive program to help ensure that  
hazards associated with the various processes are identified and controlled. Within this  
program, each process is systematically examined to identify hazards and ensure that  
adequate controls are in place to manage these hazards. 
 
The Grand Chenier gas plant primarily uses checklists to perform these evaluations.  
The analyses are conducted using a team of people who have operating and  
maintenance experience as well as engineering expertise. This team identifies and  
evaluates hazards of the process as well as accident prevention and mitigation  
measures, and the team 
makes suggestions for additional prevention and/or mitigation  
measures when the team believes such measures are necessary. 
 
The PHA team findings are resolved by local management. Implementation of mitigation  
options in response to PHA findings is based on a relative risk ranking assigned by the  
PHA team. This ranking helps ensure that potential accident scenarios assigned the  
highest risk receive immediate attention. All approved mitigation options in response to  
PHA team findings are tracked until they are completed. The final resolution of each  
finding is documented and retained. 
 
To help ensure that the process controls and/or process hazards do not eventually  
deviate significantly from the original design safety features, the plant periodically  
updates and revalidates the hazard analysis results. These periodic reviews are  
conducted at least every 5 years and will be conducted at this frequency until the  
process is no longer operating. The results and findings from thes 
e updates are  
documented and retained. Once again, the team findings are resolved by local  
management, and the final resolution of the findings is documented and retained. 
 
Operating Procedures 
 
The Grand Chenier gas plant maintains written procedures that address various modes  
of process operations, such as (1) unit startup, (2) normal operations, (3) temporary  
operations, (4) emergency shutdown, (5) normal shutdown, and (6) initial startup of a  
new process.  These procedures can be used as a reference by experienced operators  
and provide a basis for consistent training of new operators. These procedures are  
periodically reviewed and annually certified as current and accurate. The procedures  
are kept current and accurate by revising them as necessary to reflect changes made  
through the management of change process. 
 
Training 
 
To complement the written procedures for process operations, the Grand Chenier gas  
plant has implemented a comprehensive training program for all emplo 
yees involved in  
operating a process. New employees receive basic training in gas plant operations.  
After successfully completing this training, a new operator is paired with a senior  
operator to learn process-specific duties and tasks. After operators demonstrate (e.g.,  
through tests, skills demonstration) having adequate knowledge to perform the duties  
and tasks in a safe manner on their own, they can work independently. In addition, all  
operators periodically receive refresher training on the operating procedures to ensure  
that their skills and knowledge are maintained at an acceptable level. This refresher  
training is conducted at least every 3 years. All of this training is documented for each  
operator, including the means used to verify that the operator understood the training. 
 
Contractors 
 
The Grand Chenier gas plant uses contractors to supplement its workforce during  
periods of increased maintenance or construction activities. Because some contractors  
work on or ne 
ar process equipment, the gas plant has procedures in place to ensure  
that contractors (1) perform their work in a safe manner, (2) have the appropriate  
knowledge and skills, (3) are aware of the hazards in their workplace, (4) understand  
what they should do in the event of an emergency, (5) understand and follow site safety  
rules, and (6) inform gas plant personnel of any hazards that they find during their work.  
This is accomplished by providing contractors with (1) safety orientations , (2) pre-job  
safety meetings, and (3) a work permitting system. In addition, the Grand Chenier gas  
plant evaluates contractor safety programs and performance prior to the selection of a  
contractor. Gas plant personnel periodically monitor contractor performance to ensure  
that contractors are fulfilling their safety obligations. 
 
Pre-startup Safety Reviews (PSSRs) 
 
The Grand Chenier gas plant conducts a PSSR for any new facility or facility  
modification that requires a change in the process s 
afety information. The purpose of  
the PSSR is to ensure that safety features, procedures, personnel, and equipment are  
appropriately prepared for startup prior to placing the equipment into service. This  
review provides one additional check to make sure construction is in accordance with  
the design specifications and that all supporting systems are operationally ready. The  
PSSR review team uses checklists to verify all aspects of readiness. A PSSR involves  
field verification of the construction and serves a quality assurance function by requiring  
verification that accident prevention program requirements are properly implemented.   
This is part of the management of change process. 
 
Mechanical Integrity 
 
The Grand Chenier gas plant has well-established practices and procedures to maintain  
pressure vessels, piping systems, relief and vent systems, controls, pumps and  
compressors, and emergency shutdown systems in a safe operating condition. The  
basic aspects of this program inc 
lude: (1) conducting training, (2) developing written  
procedures, (3) performing inspections and tests, (4) correcting identified deficiencies,  
and (5) applying quality assurance measures. In combination, these activities form a  
system that maintains the mechanical integrity of the process. 
 
Maintenance personnel receive training on (1) an overview of the process, (2) safety  
and health hazards, (3) applicable maintenance procedures, (4) emergency response  
plans, and (5) applicable safe work practices to help ensure that they can perform their  
jobs in a safe manner. Written procedures help ensure that work is performed in a  
consistent manner and provide a basis for training. Inspections and tests are performed  
to help ensure that equipment functions as intended and to verify that equipment is  
within acceptable limits (e.g., adequate wall thickness for pressure vessels). If a  
deficiency is identified, employees will correct the deficiency before placing the  
equipment back into 
service (if possible), or a management of change team will review  
the use of the equipment and determine what actions are necessary to ensure the safe  
operation of the equipment. 
 
Another integral part of the mechanical integrity program is quality assurance. The  
Grand Chenier gas plant incorporates quality assurance measures into equipment  
purchases and repairs. This helps ensure that new equipment is suitable for its intended  
use and that proper materials and spare parts are used when repairs are made. 
 
Safe Work Practices 
 
The Grand Chenier gas plant uses the Vastar Resources safety and health manual as a  
guideline to help ensure worker and process safety. The safety manual contains  
minimum safety standards for the following operations  (1) fire and safe work permits,  
(2) lockout/tagout, (3) tagging & flagging, (4) blinding (5) vessel & confined space entry,  
(6) excavating & trenching, (7) inservice welding and hottapping. These procedures,  
along with training of personne 
l, form a system to help ensure that operations and  
maintenance activities are performed safely. 
 
Management of Change 
 
The Grand Chenier gas plant has a comprehensive system to manage all non-like-kind  
changes within the covered processes. This system requires that changes to items such  
as process equipment, chemicals, technology (including process operating conditions),  
procedures, and other facility changes be properly reviewed and authorized before  
being implemented. Changes are reviewed to (1) ensure that adequate controls are in  
place to manage any new hazards and (2) verify that existing controls have not been  
compromised by the change. Affected chemical hazard information, process operating  
limits, and equipment information, as well as procedures, are updated to incorporate  
these changes. In addition, operating and maintenance personnel are provided any  
necessary training on the change. 
 
Incident Investigation 
 
The Grand Chenier gas plant promptly investigates all inc 
idents. The goal of each  
investigation is to determine the facts and develop corrective actions to prevent a  
recurrence of the incident or a similar incident. The investigation team documents its  
findings, develops recommendations to prevent a recurrence, and forwards these  
results to gas plant management for resolution. Corrective actions taken in response to  
the investigation team's findings and recommendations are tracked until they are  
complete. The final resolution of each finding or recommendation is documented, and  
the investigation results are reviewed with all employees (including contractors) who  
could be affected by the findings. Incident investigation reports are retained for at least  
5 years so that the reports can be reviewed during future PHAs and PHA revalidations. 
 
Compliance Audits 
 
To help ensure that the accident prevention program is functioning properly, Vastar  
Resources periodically conducts an audit to determine whether the procedures and  
practices re 
quired by the accident prevention program are being implemented.  
Compliance audits are conducted at least every 3 years. Both hourly and staff  
personnel may participate as audit team members. The audit team develops findings  
that are forwarded to gas plant management for resolution. Corrective actions taken in  
response to the audit team's findings are tracked until they are complete. The final  
resolution of each finding is documented, and the two most recent audit reports are  
retained. 
 
CHEMICAL-SPECIFIC PREVENTION STEPS 
 
The processes at the Grand Chenier gas plant have hazards that must be managed to  
ensure continued safe operation. The following is a description of existing safety  
features applicable to prevention of accidental releases of regulated substances in the  
facility. 
 
Universal Prevention Activities 
 
The accident prevention program summarized previously is applied to all RMP-covered  
processes at the Grand Chenier gas plant. Collectively, these prevention program  
 
activities help prevent potential accident scenarios that could be caused by equipment  
failures and human errors. 
 
Specialized Safety Features 
 
The Grand Chenier gas plant has safety features on many units to help (1) contain/  
control a release, (2) quickly detect a release, and (3) reduce the consequences of a  
release. The following types of safety features are used in the covered processes: 
 
Release Detection 
 
1. Hydrocarbon detectors with alarms. 
 
2. Facility is manned 24 hours per day. 
 
Release Containment/Control 
 
1. Process relief valves that discharge to a flare to capture and incinerate releases 
 
2. Valves to permit isolation of the process (manual and automated) 
 
3. Automated shutdown systems for specific process parameters (e.g., high  
temperature) 
 
4. Curbing or diking to contain liquid releases 
 
5. Redundant equipment and instrumentation (e.g., uninterruptible power supply for  
process control system, backup firewater pump) 
 
6. Atmospheric relief devices. 
 
Release Mitig 
ation 
 
1. Fire suppression and extinguishing systems 
 
2. Personnel are trained in their emergency response duties 
 
3. Personal protective equipment 
 
FIVE-YEAR ACCIDENT HISTORY 
 
Vastar became operator of the Grand Chenier Gas Plant in May, 1995.  Prior to this,  
Vastar already had an ownership interest in the plant.  
 
During the period that Vastar has operated the plant, there have been no incidents  
resulting from RMP regulated substances in covered processes that have caused  
either: (1) onsite deaths, injuries, or significant property damage, or (2) offsite deaths,  
injuries, property damage, evacuations, sheltering in place, or environmental damage.  
To Vastars knowledge, there were no such incidents during the balance of the five year  
period; that is, the year or so prior to Vastar becoming operator. 
 
EMERGENCY RESPONSE PROGRAM INFORMATION 
 
The Grand Chenier gas plant maintains a written emergency response program, which  
is in place to protect both plant personnel and the public 
. The program consists of  
procedures for responding to an incident, including the possibility of a fire or explosion if  
a flammable substance is accidentally released. The procedures address all aspects of  
emergency response, including proper first aid and medical treatment for exposures,  
evacuation plans and accounting for personnel after an evacuation, notification of local  
emergency response agencies and the public if a release occurs, and post-incident  
cleanup and decontamination requirements. In addition, the plant has procedures that  
address maintenance, inspection, and testing of emergency response equipment, as  
well as instructions that address the use of emergency response equipment. Employees  
receive training in these procedures as necessary to perform their specific emergency  
response duties. The emergency response program is updated when necessary based  
on modifications made to gas plant processes. Affected personnel or informed and/or  
trained, as appropriate, r 
egarding the changes.  
 
The overall emergency response program for the Grand Chenier gas plant is  
coordinated with the Cameron Parish Civil Defense Local Emergency Planning  
Committee (LEPC). This coordination includes periodic meetings with local emergency  
response officials. The Grand Chenier gas plant has around-the-clock communications  
capability with appropriate LEPC officials and emergency response organizations (e.g.,  
fire department). This provides a means of notifying the public of an incident, if  
necessary, as well as facilitating quick response to an incident. The Grand Chenier gas  
plant conducts periodic emergency drills that involve the LEPC and emergency  
response organizations.  
 
PLANNED CHANGES TO IMPROVE SAFETY 
 
The Grand Chenier gas plant resolves all findings from PHAs, some of which result in  
modifications to the process. The following types of changes are planned over the next  
few years in response to PHA, safety audit, and incident investigation findings: 
 
 
1. Upgraded process control system to use distributed computerized control system, 
 
2. Revised personnel training programs, and 
 
3. Revised written operating procedures.
Click to return to beginning